A good inspection report template has seven parts: cover details (site, client, inspector, date), the scope of what was and was not inspected, a summary with counts of findings by priority, a numbered findings table, photos tied to each finding, recommendations, and a sign-off. Copy the structure below, then adapt the categories for snagging, health and safety, property condition or quality audits.

Man reviewing architectural plans at desk in sunlight, displaying concentration and creativity

What goes in an inspection report

Most inspection reports are read twice: once by the person who has to fix things, and again months later by someone trying to work out what was found, when, and whether it was dealt with. A template that works for both readers has the same seven sections every time, in the same order.

  1. Cover details: what was inspected, where, for whom, by whom and when.
  2. Scope and limitations: what you looked at, what you did not, and why.
  3. Summary of findings: a short paragraph plus counts by priority, so a manager can read one page and know how bad it is.
  4. Findings table: one numbered row per finding, with location, description, priority, action, owner and due date.
  5. Photos: each photo labelled with the finding number it belongs to.
  6. Recommendations: what should happen next, in order.
  7. Sign-off: name, role, signature and date for the inspector, and for the person accepting the report if needed.

The rest of this page gives the fields for each section, a filled example, and the changes to make for different kinds of inspection.

The template, section by section

1. Cover details

FieldWhat to write
Report titleType of inspection and site, e.g. Pre-handover inspection, Plot 14
Report referenceYour own numbering, e.g. IR-2026-031, so later reports can refer back
Site addressFull address, plus plot, unit, block or floor
ClientWho the inspection was carried out for
Inspected byName, role and company
Date and timeStart and finish time, not just the date
Others presentNames and companies, if anyone walked round with you
ConditionsWeather, lighting, occupied or empty, services on or off
Reference documentsDrawings, specifications or previous reports you checked against

2. Scope and limitations

Two short lists. Included: the areas, elements or systems you inspected. Excluded or not accessible: roof spaces you could not enter, rooms that were locked, services you could not test, anything hidden behind finishes. This is the part people skip, and it is the part that protects the inspector when someone later asks why a defect was not reported.

3. Summary of findings

Three or four sentences on the overall condition, followed by a count table:

PriorityCountMeaning
Critical0Unsafe or stops work, occupation or handover; act now
High0Must be fixed before the next milestone
Medium0Fix within an agreed period
Low0Cosmetic or minor; fix when convenient
Total0

Agree what each priority means with the client before you start, and print the definitions in the report so nobody argues about them later.

4. Findings table

These columns copy straight into a spreadsheet:

No.LocationFindingCategory / tradePriorityPhotoAction requiredOwnerDueStatus
1Room, level, gridlineWhat is wrong, in one or two sentencese.g. ElectricalHigh1a, 1bWhat fixed looks likeName or companyDateOpen

Keep the status column to a short fixed list such as Open, In progress, Fixed and Closed. Fixed means the person responsible says it is done; Closed means someone has checked it.

5. Photos

Label each photo with its finding number (1a, 1b, 2a). Put them either under each finding or in an appendix, but not both.

6. Recommendations

A numbered list of next steps: urgent actions first, then further investigation (for example, a specialist survey), then a date for a re-inspection.

7. Sign-off

Inspector name, role, signature and date. If the report is accepted by a client, contractor or site manager, add a second block for them, with a line saying what they are accepting (receipt of the report, not agreement that every finding is correct, unless that is what you both mean).

Filled example: pre-handover inspection of a new-build flat

Cover: Pre-handover inspection, Flat 3, Block B, Riverside Court. Reference IR-2026-031. Client: the main contractor's project manager. Inspected by: site inspector. Date: 12 November 2026, 09:30 to 11:15. Conditions: dry, overcast; electricity on, water on, heating not commissioned. Checked against: architect's room finishes schedule, revision C.

Scope: all rooms, internal doors, kitchen, bathroom, en suite, windows, balcony. Not inspected: heating system (not commissioned), communal areas, roof.

Summary: The flat is close to complete. Finishes are generally good. One high-priority electrical item and a balcony balustrade fixing need attention before handover; the rest are minor decorating and adjustment items.

No.LocationFindingTradePriorityActionOwnerDue
1BalconyGlass balustrade: one fixing bolt at the left-hand post is loose and the cover cap is missingMetalworkCriticalTighten and check all fixings, fit cap; keep balcony door locked until doneBalustrade installer13 Nov
2Bedroom 2Double socket behind door has no faceplate; live terminals exposedElectricalHighFit faceplate and testElectrician14 Nov
3BathroomSilicone bead along bath edge is gapped for about 200 mm at the tap endPlumbingMediumRemove and reseal full lengthPlumber19 Nov
4KitchenWall unit door above hob rubs on adjacent door when openedJoineryLowAdjust hingesKitchen fitter19 Nov
5HallwayPaint run on skirting next to the front door, about 50 mm longDecoratingLowSand and repaintDecorator19 Nov
6Living roomWindow restrictor on right-hand casement does not engageWindowsHighAdjust or replace restrictorWindow installer14 Nov

Counts: Critical 1, High 2, Medium 1, Low 2. Total 6.

Recommendations: (1) Lock the balcony door until item 1 is fixed and checked. (2) Complete items 2 and 6 before handover. (3) Re-inspect on 20 November and close items that are confirmed fixed. (4) Inspect the heating system once commissioned.

Sign-off: inspector's name, signature and date; project manager's name, signature and date for receipt.

Variants: adapting the template

The structure stays the same. What changes is the category list, the priority definitions and the reference documents.

Inspection typeTypical categoriesChecked againstWhat to add
Snagging (new build or fit-out)Trades: decorating, joinery, plumbing, electrical, flooringDrawings, finishes schedule, specification, warranty standardsRoom-by-room order; a re-inspection column. See the snagging list template
Health and safetyAccess, housekeeping, work at height, PPE, plant, fire, welfareRisk assessments, method statements, construction phase plan, HSE guidanceImmediate action taken on site, and who was told. See the site inspection report guide
Property conditionElements: roof, walls, windows, services, damp, internal finishesPrevious reports, lease or tenancy termsA condition rating per element, and an estimated urgency rather than an owner
Quality auditSpecification clauses or work packagesSpecification, approved samples, manufacturer instructionsA pass / fail / observation column and the clause number for each finding

For a property condition report you may not know who will fix anything, so replace the owner and due columns with urgency (now, within 12 months, monitor). For a quality audit, the finding should name the requirement it fails, otherwise the contractor will treat it as opinion.

How to write a good finding

A finding is good when someone who was not there can find it, understand it and know when it is fixed. Four rules cover most of it:

WeakBetter
Bad paint in loungeLiving room, wall opposite window: roller marks and patchy coverage across about 1 m², visible in daylight
Door sticksBedroom 1 door binds on head of frame at latch side; needs 2 mm planing and repainting of the edge
Scaffold issueNorth elevation, lift 3: toe board missing for 2 m at the corner; area taped off at 10:20 and scaffold contractor told

One finding per row. If a door has three problems, that is three rows, because three different people may fix them on three different days.

Close-up of a textured wall with prominent cracks and stains
Describe what you can see and measure it, rather than guessing the cause.

Photos that make the report usable

Construction worker in safety gear checking smartphone on a Detroit site
Take a close-up and a wider photo for every finding that matters.

Common mistakes

Filling it in on a phone

You can use this template in a spreadsheet, a word processor or on paper. If you would rather record findings on your phone as you walk round, Snagline (iPhone and Android, not released yet) numbers each issue, keeps its photos, priority, location, owner and due date together, and produces a PDF with a cover, issue counts and a signed sign-off, or a CSV for Excel. It works offline. You can join the waitlist below.

Questions

What should be included in an inspection report?

Cover details (site, client, inspector, date and time), scope and limitations, a summary with counts by priority, a numbered findings table, photos linked to each finding, recommendations and a sign-off.

How do you write an inspection report?

Record findings on site as you go, one per row, location first, describing what you see and measuring where you can. Then write the summary and recommendations, check the counts, and sign it off.

What is the difference between an inspection report and a snag list?

A snag list is one kind of inspection report, focused on defects and unfinished work before handover. A general inspection report can also cover safety, condition or compliance, and usually has a scope section and recommendations.

Should an inspection report include photos?

Yes, for anything that needs action. Label each photo with its finding number and include a wider shot that shows where the defect is.

Can I use this inspection report template in Excel or Word?

Yes. The findings table columns copy straight into a spreadsheet, and the cover, scope, summary and sign-off sections work as headings in a document.