Snag list: what it is, what goes on it and how to write one that gets fixed

Updated · Snagline guides

A snag list (or snagging list) is a written list of small defects and unfinished items in a building that need putting right before, or soon after, it is handed over. Each entry says where the problem is, what is wrong and who should fix it, usually with a photo, so the builder can find it, fix it and sign it off.

Close-up of a textured wall with prominent cracks and stains

What is a snag list?

A snag is a minor fault: something damaged, broken, badly fitted or left looking unfinished. A paint run on a skirting board, a door that will not latch, a tap fitted the wrong way round, a missing socket cover. None of them stop you living in the building, but together they decide whether the work looks finished.

A snag list collects every one of those faults in one place. On a new home it is written by the buyer or an inspector they hire. On a commercial or refurbishment job it is usually written by the site manager, the client's surveyor or the architect, and the contractor works through it trade by trade. The same document goes by several names: snag list, snagging list, snag sheet, defects list and, in the US, a punch list.

A good snag list is not a complaint letter. It is a work order. Each line should be specific enough that someone who has never been in the building can walk to the spot, see the fault and know what "fixed" looks like.

What goes on a snag list

Every entry needs the same handful of fields. Keep them as columns if you use a spreadsheet, or as headings if you write by hand:

If you want a ready-made layout with these columns, use our snagging list template.

How to write snag entries a builder can act on

Most arguments about snags come from vague entries. "Paintwork poor" invites a shrug. "Landing: paint run on skirting board, 30 cm left of bathroom door" gets a decorator to the right place with the right brush. Follow four rules:

  1. Location first, from big to small. Floor, room, wall or element, then position. Use fixed reference points: doors, windows, sockets, radiators.
  2. Say what is wrong, not how you feel about it. "Gap of about 3 mm between worktop and wall tiles, no sealant" is a fact. "Shoddy kitchen" is not.
  3. One fault per entry. If a bathroom has a cracked tile and a loose toilet seat, that is two snags with two trades. Combined entries get half-fixed and closed.
  4. Photograph it the way you described it. A close-up alone is useless if nobody can tell which wall it is on. Mark the spot with an arrow or circle if you can.

Real example entries

Here is how good entries read. Each one could be handed to a tradesperson without a phone call:

Notice what they have in common: a room, a precise spot, a measurement where it helps, a trade and a reason for the priority when it is not obvious.

Confident female construction worker inspecting site with clipboard and helmet
Write the location and the fault at the spot, while you can see it.

Setting priorities that mean something

If everything is High, nothing is. A simple scale works on almost every job:

PriorityUse it forExamples
CriticalUnsafe, or causing damage nowExposed live wires, leaking pipe, broken stair balustrade, no heating in winter
HighAffects security, weathertightness or useWindow will not lock, front door lets water in, missing bath sealant
MediumWorks, but not properlyDoor catches its frame, extractor fan not wired to light, scraping garage door
LowCosmeticPaint runs, scuffs, small plaster cracks, missing screw caps

On a new home, anything that is a genuine emergency (no water, no heating, a gas smell, an electrical danger) should be reported straight away by phone using the builder's emergency contact, not left on a list.

Who uses snag lists

Homeowners buying a new build

Buyers write a snag list during a pre-completion inspection, at handover and again as things show up in the first months. Developers registered with the New Homes Quality Code must give buyers the chance to have that pre-completion inspection and must deal with snags reported in the first two years after completion. Our guide to what snagging is covers those rights, and the new build snagging checklist lists what to inspect room by room.

Developers and housebuilders

Site teams run their own internal snagging before a plot is shown to the buyer. A plot that leaves with a short buyer list means fewer return visits from trades and fewer customer care calls.

Contractors and subcontractors

On fit-outs, refurbishments and commercial jobs, the main contractor snags each area before inviting the client to inspect, then receives the client's own list. Subcontractors get the lines for their trade, fix them and report back.

Site managers, surveyors and clerks of works

They write the list, chase it and decide when an item is closed. For them the snag list is also a record: who reported what, when it was fixed and who checked it.

When to make a snag list

A woman stands on a ladder painting a wall white, part of a DIY home renovation
Most snags are finishing work: decoration, sealant, ironmongery and small adjustments.

Sample snag list

A short list for a three-bedroom new build, as it might look a week after handover. Copy the columns into a spreadsheet or use the full template.

No.LocationDescriptionTradePriorityStatus
1Kitchen, sink unitDrip from waste connection under sink, cupboard base wetPlumberCriticalIn progress
2Lounge, rear windowWindow will not lock closed, handle stiffWindowsHighOpen
3Bathroom, bathSilicone missing at tap end, about 20 cmPlumberHighFixed
4Bedroom 2, behind doorSocket cover missing, wires visibleElectricianHighClosed
5Bedroom 1, wardrobe wallPatch of uneven plaster visible in daylight, about 40 cm widePlastererMediumOpen
6Hall, above front doorPlaster crack about 25 cmPlastererLowOpen
7Landing, skirtingPaint run 30 cm left of bathroom doorDecoratorLowOpen
8Front elevationMortar missing below lounge window sillBricklayerMediumOpen

Paper snag list or digital?

Paper still works for a one-bedroom flat: a clipboard, a pen and a phone for photos. The trouble starts afterwards. Photos sit in a camera roll with no link to the line they belong to, the list gets retyped into an email, and nobody is sure which version is current.

A spreadsheet fixes the version problem but is awkward on site. A snagging app puts the photo, the location and the entry together at the moment you find the fault, numbers entries for you and turns the list into a report you can send. Whichever you use, the rules above matter more than the tool.

Snagline is a phone app we are building for exactly this: snap the defect first, describe it, set the trade and priority, pin it on a floor plan and share a PDF report. It is not released yet; you can join the waitlist below.

Common snag list mistakes

Questions

What is the difference between a snag list and a snagging list?

Nothing. Snag list, snagging list, snag sheet and defects list all mean the same thing: a list of minor faults to put right. In the US it is usually called a punch list.

What should be included in a snag list?

For each fault: a number, the location, a short description, the trade responsible, a priority, a photo, the date raised, a due date, the status and who signed it off.

Who writes the snag list on a new build?

The buyer or a snagging inspector they appoint writes it, and sends it to the developer's customer care or after-sales team. The developer's site team will also have snagged the home before handover.

How long do I have to send a snag list to my builder?

Send it as soon as you can. Under the New Homes Quality Code the developer is responsible for snags and defects reported in the first two years after completion, but reporting early gets faults fixed while trades are still on site. Check your own contract and warranty.

Can I use my phone to make a snag list?

Yes. Take a wide photo to show the location and a close-up of the fault, and note the room, the fault and the trade straight away. A snagging app keeps the photos attached to each entry.