Snag list: what it is, what goes on it and how to write one that gets fixed
A snag list (or snagging list) is a written list of small defects and unfinished items in a building that need putting right before, or soon after, it is handed over. Each entry says where the problem is, what is wrong and who should fix it, usually with a photo, so the builder can find it, fix it and sign it off.

What is a snag list?
A snag is a minor fault: something damaged, broken, badly fitted or left looking unfinished. A paint run on a skirting board, a door that will not latch, a tap fitted the wrong way round, a missing socket cover. None of them stop you living in the building, but together they decide whether the work looks finished.
A snag list collects every one of those faults in one place. On a new home it is written by the buyer or an inspector they hire. On a commercial or refurbishment job it is usually written by the site manager, the client's surveyor or the architect, and the contractor works through it trade by trade. The same document goes by several names: snag list, snagging list, snag sheet, defects list and, in the US, a punch list.
A good snag list is not a complaint letter. It is a work order. Each line should be specific enough that someone who has never been in the building can walk to the spot, see the fault and know what "fixed" looks like.
What goes on a snag list
Every entry needs the same handful of fields. Keep them as columns if you use a spreadsheet, or as headings if you write by hand:
- Number: a unique reference (1, 2, 3…) so everyone can talk about "snag 14" without confusion.
- Location: room or area, then the exact spot. "Bedroom 2, wall behind door" beats "upstairs".
- Description: what is wrong, in one plain sentence.
- Trade: who fixes it: decorator, joiner, electrician, plumber, plasterer, tiler, roofer, groundworker.
- Priority: how urgent. Low, Medium, High, and Critical for anything unsafe or causing damage.
- Photo: at least one picture, ideally a wide shot to show where and a close-up to show what.
- Date raised and due date: so you can tell what is overdue.
- Status: Open, In progress, Fixed, Closed.
- Signed off: who checked the fix and when.
If you want a ready-made layout with these columns, use our snagging list template.
How to write snag entries a builder can act on
Most arguments about snags come from vague entries. "Paintwork poor" invites a shrug. "Landing: paint run on skirting board, 30 cm left of bathroom door" gets a decorator to the right place with the right brush. Follow four rules:
- Location first, from big to small. Floor, room, wall or element, then position. Use fixed reference points: doors, windows, sockets, radiators.
- Say what is wrong, not how you feel about it. "Gap of about 3 mm between worktop and wall tiles, no sealant" is a fact. "Shoddy kitchen" is not.
- One fault per entry. If a bathroom has a cracked tile and a loose toilet seat, that is two snags with two trades. Combined entries get half-fixed and closed.
- Photograph it the way you described it. A close-up alone is useless if nobody can tell which wall it is on. Mark the spot with an arrow or circle if you can.
Real example entries
Here is how good entries read. Each one could be handed to a tradesperson without a phone call:
- Kitchen: wall cupboard door left of extractor drops 4 mm at the handle side and catches the next door. Joiner. Medium.
- Bedroom 2: socket cover missing behind door, wires visible. Electrical. High.
- Bathroom: silicone around bath missing at tap end, about 20 cm. Plumber. High (water can get behind the bath).
- Hall: plaster crack above front door, about 25 cm, running towards the ceiling. Plasterer. Low.
- Lounge: window handle stiff, window will not lock in the closed position. Windows. High (security).
- Landing: paint run on skirting board, 30 cm left of bathroom door. Decorator. Low.
- En-suite: extractor fan does not run when the light is switched on. Electrical. Medium.
- Rear garden: standing water on patio by back door after rain, paving falls towards the house. Groundworks. High.
- Garage: up-and-over door scrapes the frame on the right-hand side when opening. Garage doors. Medium.
- Front elevation: mortar missing from joint below lounge window sill. Bricklayer. Medium.
Notice what they have in common: a room, a precise spot, a measurement where it helps, a trade and a reason for the priority when it is not obvious.

Setting priorities that mean something
If everything is High, nothing is. A simple scale works on almost every job:
| Priority | Use it for | Examples |
|---|---|---|
| Critical | Unsafe, or causing damage now | Exposed live wires, leaking pipe, broken stair balustrade, no heating in winter |
| High | Affects security, weathertightness or use | Window will not lock, front door lets water in, missing bath sealant |
| Medium | Works, but not properly | Door catches its frame, extractor fan not wired to light, scraping garage door |
| Low | Cosmetic | Paint runs, scuffs, small plaster cracks, missing screw caps |
On a new home, anything that is a genuine emergency (no water, no heating, a gas smell, an electrical danger) should be reported straight away by phone using the builder's emergency contact, not left on a list.
Who uses snag lists
Homeowners buying a new build
Buyers write a snag list during a pre-completion inspection, at handover and again as things show up in the first months. Developers registered with the New Homes Quality Code must give buyers the chance to have that pre-completion inspection and must deal with snags reported in the first two years after completion. Our guide to what snagging is covers those rights, and the new build snagging checklist lists what to inspect room by room.
Developers and housebuilders
Site teams run their own internal snagging before a plot is shown to the buyer. A plot that leaves with a short buyer list means fewer return visits from trades and fewer customer care calls.
Contractors and subcontractors
On fit-outs, refurbishments and commercial jobs, the main contractor snags each area before inviting the client to inspect, then receives the client's own list. Subcontractors get the lines for their trade, fix them and report back.
Site managers, surveyors and clerks of works
They write the list, chase it and decide when an item is closed. For them the snag list is also a record: who reported what, when it was fixed and who checked it.
When to make a snag list
- Before completion or practical completion. The best time. Faults found before handover are fixed while trades are still on site.
- At handover. Walk through with the builder or site manager and agree the list on the day if you can.
- In the first weeks of living in or using the building. Some faults only show with use: a shower tray that leaks, radiators that do not heat, a door that sticks once the heating dries the timber.
- Before the end of the defects period. Building contracts often have a defects or rectification period after completion, commonly six or twelve months, set by the contract. On a new home the developer's after-sales period under the New Homes Quality Code is two years. Do a final walk-round before it ends and report everything outstanding in writing.

Sample snag list
A short list for a three-bedroom new build, as it might look a week after handover. Copy the columns into a spreadsheet or use the full template.
| No. | Location | Description | Trade | Priority | Status |
|---|---|---|---|---|---|
| 1 | Kitchen, sink unit | Drip from waste connection under sink, cupboard base wet | Plumber | Critical | In progress |
| 2 | Lounge, rear window | Window will not lock closed, handle stiff | Windows | High | Open |
| 3 | Bathroom, bath | Silicone missing at tap end, about 20 cm | Plumber | High | Fixed |
| 4 | Bedroom 2, behind door | Socket cover missing, wires visible | Electrician | High | Closed |
| 5 | Bedroom 1, wardrobe wall | Patch of uneven plaster visible in daylight, about 40 cm wide | Plasterer | Medium | Open |
| 6 | Hall, above front door | Plaster crack about 25 cm | Plasterer | Low | Open |
| 7 | Landing, skirting | Paint run 30 cm left of bathroom door | Decorator | Low | Open |
| 8 | Front elevation | Mortar missing below lounge window sill | Bricklayer | Medium | Open |
Paper snag list or digital?
Paper still works for a one-bedroom flat: a clipboard, a pen and a phone for photos. The trouble starts afterwards. Photos sit in a camera roll with no link to the line they belong to, the list gets retyped into an email, and nobody is sure which version is current.
A spreadsheet fixes the version problem but is awkward on site. A snagging app puts the photo, the location and the entry together at the moment you find the fault, numbers entries for you and turns the list into a report you can send. Whichever you use, the rules above matter more than the tool.
Snagline is a phone app we are building for exactly this: snap the defect first, describe it, set the trade and priority, pin it on a floor plan and share a PDF report. It is not released yet; you can join the waitlist below.
Common snag list mistakes
- Vague locations. "Upstairs" or "bedroom" when there are three bedrooms.
- Several faults in one line. Half gets fixed, the line gets closed.
- No photos, or photos with no context. A close-up of a scratch could be any door in the house.
- Inspecting in poor light. Plaster and paint faults hide under artificial light and show in daylight. The New Homes Quality Code's inspection checklist guidance, for example, says internal walls should be looked at in natural daylight from at least two metres, without shining a torch on the surface.
- Nothing in writing. A snag mentioned to a site operative in passing has not been reported. Send the list, keep a copy and note the date.
- Closing items without checking. Mark an item Fixed when the trade says so, and Closed only when you have seen it yourself.
Questions
What is the difference between a snag list and a snagging list?
Nothing. Snag list, snagging list, snag sheet and defects list all mean the same thing: a list of minor faults to put right. In the US it is usually called a punch list.
What should be included in a snag list?
For each fault: a number, the location, a short description, the trade responsible, a priority, a photo, the date raised, a due date, the status and who signed it off.
Who writes the snag list on a new build?
The buyer or a snagging inspector they appoint writes it, and sends it to the developer's customer care or after-sales team. The developer's site team will also have snagged the home before handover.
How long do I have to send a snag list to my builder?
Send it as soon as you can. Under the New Homes Quality Code the developer is responsible for snags and defects reported in the first two years after completion, but reporting early gets faults fixed while trades are still on site. Check your own contract and warranty.
Can I use my phone to make a snag list?
Yes. Take a wide photo to show the location and a close-up of the fault, and note the room, the fault and the trade straight away. A snagging app keeps the photos attached to each entry.