Punch list template: columns, a filled-in example and how to use it

Updated · Snagline guides

A good punch list template has one row per item and these columns: item number, location, description, trade, responsible party, priority, photo reference, date added, due date, status and verified by/date. Copy the layout below into Excel or Google Sheets, use the filled-in example as a guide, and run your punch walk room by room.

A woman stands on a ladder painting a wall white, part of a DIY home renovation

The punch list template columns

These eleven columns cover what a general contractor (GC), the subs and the architect need to know about each item. Copy the headers straight into row 1 of a spreadsheet.

ColumnWhat to put in itExample
Item #A running number that never changes once issued, so "item 47" means the same thing to everyone47
Location / RoomBuilding, level, room or gridline. Be specific enough that a sub can walk straight to itLevel 2, Room 214, north wall
DescriptionWhat is wrong and what "done" looks likeOutlet cover plate missing; install ivory plate
Trade / SubThe trade that does the fixElectrical
Responsible partyThe company (and ideally the person) who owns the itemBright Electric, Mike R.
PriorityCritical (safety, code or blocks occupancy), High, Medium, LowHigh
Photo refPhoto number or file name, with the defect markedP-047
Date addedWhen the item went on the list10/12
DueAgreed fix date; often set by the substantial completion certificate or the GC10/19
StatusOpen, In progress, Ready for review, Closed (or Rejected if a fix fails)Open
Verified by / DateInitials of whoever checked the fix on site, and whenJM 10/17

If you only want a quick list for a small job, keep Item #, Location, Description, Trade, Status and add the others as the list grows. Drop columns before you drop detail in the description: a precise description matters more than any column.

Filled-in punch list example

Here is what the template looks like a few days after the punch walk on a small mixed-use building: a few residential units over a ground-floor office suite. Names are made up; the entries are the kind you will actually write.

#LocationDescriptionTradeResponsiblePriorityPhotoAddedDueStatusVerified
1Unit 204, KitchenDishwasher not secured to underside of countertopPlumbingABC PlumbingHighP-00110/1210/16Open
2Unit 204, BathGrout missing at tub/wall corner, 6 in. runTileCoastal TileMediumP-00210/1210/19In progress
3Corridor 2BCeiling tile stained next to sprinkler head, replace tile, check for leakAcoustical ceilingsSummit CeilingsHighP-00310/1210/14Ready for review
4Lobby, Door 101Closer slams, adjust closing and latch speedDoor hardwareKeystone DoorsMediumP-00410/1210/16ClosedJM 10/15
5Suite 300, Conf. RoomTwo outlet cover plates missing, east wallElectricalBright ElectricLowP-00510/1210/19ClosedJM 10/17
6Suite 300, Break RoomUpper cabinet door misaligned, rubs adjacent doorMillworkOakline MillworkLowP-00610/1210/19Open
7Stair 1, Level 2Exit sign not lit on battery testElectricalBright ElectricCriticalP-00710/1210/13Ready for review
8Primary BedroomPaint: roller marks on north wall at eye height, repaint wallPaintingProFinish PaintingMediumP-00810/1210/19Open
9Entry, ExteriorSealant gap at storefront frame, left jambGlazingClearview GlassHighP-00910/1210/16In progress
10Mech. Room 010Panel schedule not filled in, Panel LP-1ElectricalBright ElectricMedium—10/1210/19Open

Notice what makes these entries useful. Each one says where (down to the wall or door number), what is wrong and, where it is not obvious, what done looks like ("repaint wall", "check for leak"). The exit sign is Critical because it is a life-safety item that can hold up occupancy. Items 4 and 5 are closed only because someone checked them on site and initialed them.

How to set up the template in Excel or Google Sheets

Template variants for different jobs

Residential remodel punch list

On a kitchen, bath or whole-house remodel the homeowner usually walks with the GC. Keep it simple: Room, Item, Trade, Status, Homeowner OK. The extra "Homeowner OK" column, initialed by the owner, records that they accept the fix, which helps when the final payment depends on the list being cleared. Group the list by room: kitchen, primary bath, hall bath, bedrooms, exterior.

Commercial tenant improvement (TI) punch list

A TI job has more parties: the GC, the tenant, the landlord's representative and often the architect. Add a Raised by column (Architect, Tenant, Landlord, GC) and a Spec / drawing ref column so items tie back to the contract documents. Split the list by area (open office, conference rooms, break room, restrooms, corridors) and keep landlord base-building items separate from tenant-scope items, since different people pay for them.

Room-by-room punch list

For multifamily, hotels and dorms, the same rooms repeat. Make one sheet per unit or room, with the categories pre-filled down the left side: walls and paint, ceiling, floor, doors and hardware, windows, electrical, plumbing, HVAC, millwork, cleaning. The person walking ticks each category as OK or writes an item. Pre-filled categories stop people from skipping the ceiling or the back of the door.

VariantColumns to add or dropGroup by
Residential remodelAdd Homeowner OK; drop Responsible party if the GC handles all tradesRoom
Commercial TIAdd Raised by, Spec/drawing ref, Scope (tenant or landlord)Area or suite
Room-by-roomPre-filled category rows per room; Status per categoryUnit or room number
Man reviewing architectural plans at desk in sunlight, displaying concentration and creativity
Set up the template once and reuse it on every job.

How to run the punch walk with this template

  1. Walk it yourself first. The GC and superintendent do an internal walk before the architect or owner sees the job. Fix the obvious items before the formal walk so the official list stays short.
  2. Agree the route and the people. Set a time with the architect, owner's rep and key subs. Walk in a fixed order, such as top floor down, clockwise in each room, so nothing is skipped.
  3. Bring what you need. A printed or digital copy of the template, the floor plans, a phone or camera, painter's tape or dot stickers to mark items, a flashlight and a level.
  4. Write each item where you stand. Location, defect, trade. Take the photo and note its number in the same moment. Don't rely on memory back at the trailer.
  5. Mark the defect physically. A small piece of tape or a sticker with the item number lets the sub find it without the list.
  6. Settle disputes on the spot or park them. If someone says an item is new scope, note it as "disputed" and move on. Resolve it through a change order later, not on the walk.
  7. Issue the list the same day. Clean it up, assign every item to a sub with a due date, and send it out as a PDF while the walk is fresh.

For background on where the punch walk fits between substantial completion and final completion, see what is a punch list.

How to close out punch list items

The list is only useful if items move to Closed in a way everyone trusts. A simple workflow:

  1. Open: item written and assigned.
  2. In progress: the sub has started or scheduled the fix.
  3. Ready for review: the sub says it is done, ideally with an "after" photo.
  4. Closed: the GC (or the architect, for items they raised) checks it on site and initials and dates the Verified column.

If a fix fails review, set it back to Open with a note ("still rubs at head") rather than writing a new item, so the history stays on one line. Before asking for the final inspection, filter for anything not Closed, walk those items again and attach the updated list to your request. Keep the final version, with photos, in the closeout file alongside warranties and lien waivers: it is your record of what was fixed and when.

Common template mistakes

From spreadsheet to phone

The spreadsheet works, but on site you end up writing notes, taking photos on a phone and typing it all up later. A punch list app puts the photo, the location and the item in one place as you walk. Snagline, our phone app for punch lists and site audits, numbers items for you, pins them on the floor plan and exports a PDF report or a CSV file for Excel. It is not released yet; join the waitlist below.

Questions

What should be included in a punch list template?

At minimum an item number, location, description, trade and status. Most GCs also add the responsible sub, priority, photo reference, date added, due date and who verified the fix.

How do you write a punch list item?

Write the location, the defect and what done looks like, then assign the trade: for example, Room 214, north wall: outlet cover plate missing, install plate, Electrical. Add a photo with the defect marked.

Is there a punch list template in Excel?

You can build one in a few minutes: paste the eleven column headers from this page into row 1, add drop-downs for Priority and Status, and freeze the header row. The same layout works in Google Sheets.

Who fills out the punch list?

The general contractor usually writes and maintains it, with items added by the architect and owner during the punch walk. Subs update the status of their own items, and the GC or architect verifies and closes them.

What is the difference between a punch list and a checklist?

A checklist lists what to inspect, such as walls, doors and fixtures, before anyone looks. A punch list lists what was actually found wrong and must be fixed.