Punch list template: columns, a filled-in example and how to use it
A good punch list template has one row per item and these columns: item number, location, description, trade, responsible party, priority, photo reference, date added, due date, status and verified by/date. Copy the layout below into Excel or Google Sheets, use the filled-in example as a guide, and run your punch walk room by room.

The punch list template columns
These eleven columns cover what a general contractor (GC), the subs and the architect need to know about each item. Copy the headers straight into row 1 of a spreadsheet.
| Column | What to put in it | Example |
|---|---|---|
| Item # | A running number that never changes once issued, so "item 47" means the same thing to everyone | 47 |
| Location / Room | Building, level, room or gridline. Be specific enough that a sub can walk straight to it | Level 2, Room 214, north wall |
| Description | What is wrong and what "done" looks like | Outlet cover plate missing; install ivory plate |
| Trade / Sub | The trade that does the fix | Electrical |
| Responsible party | The company (and ideally the person) who owns the item | Bright Electric, Mike R. |
| Priority | Critical (safety, code or blocks occupancy), High, Medium, Low | High |
| Photo ref | Photo number or file name, with the defect marked | P-047 |
| Date added | When the item went on the list | 10/12 |
| Due | Agreed fix date; often set by the substantial completion certificate or the GC | 10/19 |
| Status | Open, In progress, Ready for review, Closed (or Rejected if a fix fails) | Open |
| Verified by / Date | Initials of whoever checked the fix on site, and when | JM 10/17 |
If you only want a quick list for a small job, keep Item #, Location, Description, Trade, Status and add the others as the list grows. Drop columns before you drop detail in the description: a precise description matters more than any column.
Filled-in punch list example
Here is what the template looks like a few days after the punch walk on a small mixed-use building: a few residential units over a ground-floor office suite. Names are made up; the entries are the kind you will actually write.
| # | Location | Description | Trade | Responsible | Priority | Photo | Added | Due | Status | Verified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Unit 204, Kitchen | Dishwasher not secured to underside of countertop | Plumbing | ABC Plumbing | High | P-001 | 10/12 | 10/16 | Open | |
| 2 | Unit 204, Bath | Grout missing at tub/wall corner, 6 in. run | Tile | Coastal Tile | Medium | P-002 | 10/12 | 10/19 | In progress | |
| 3 | Corridor 2B | Ceiling tile stained next to sprinkler head, replace tile, check for leak | Acoustical ceilings | Summit Ceilings | High | P-003 | 10/12 | 10/14 | Ready for review | |
| 4 | Lobby, Door 101 | Closer slams, adjust closing and latch speed | Door hardware | Keystone Doors | Medium | P-004 | 10/12 | 10/16 | Closed | JM 10/15 |
| 5 | Suite 300, Conf. Room | Two outlet cover plates missing, east wall | Electrical | Bright Electric | Low | P-005 | 10/12 | 10/19 | Closed | JM 10/17 |
| 6 | Suite 300, Break Room | Upper cabinet door misaligned, rubs adjacent door | Millwork | Oakline Millwork | Low | P-006 | 10/12 | 10/19 | Open | |
| 7 | Stair 1, Level 2 | Exit sign not lit on battery test | Electrical | Bright Electric | Critical | P-007 | 10/12 | 10/13 | Ready for review | |
| 8 | Primary Bedroom | Paint: roller marks on north wall at eye height, repaint wall | Painting | ProFinish Painting | Medium | P-008 | 10/12 | 10/19 | Open | |
| 9 | Entry, Exterior | Sealant gap at storefront frame, left jamb | Glazing | Clearview Glass | High | P-009 | 10/12 | 10/16 | In progress | |
| 10 | Mech. Room 010 | Panel schedule not filled in, Panel LP-1 | Electrical | Bright Electric | Medium | — | 10/12 | 10/19 | Open |
Notice what makes these entries useful. Each one says where (down to the wall or door number), what is wrong and, where it is not obvious, what done looks like ("repaint wall", "check for leak"). The exit sign is Critical because it is a life-safety item that can hold up occupancy. Items 4 and 5 are closed only because someone checked them on site and initialed them.
How to set up the template in Excel or Google Sheets
- Put the headers in row 1 and freeze the row so it stays visible as you scroll
- Make Priority and Status drop-down lists (Data validation) so everyone uses the same words
- Format the Due column as dates and add conditional formatting to flag overdue items that are not Closed
- Turn on a filter so each sub can see only their trade
- Add a header block above the table: project name, address, contract or job number, punch walk date, who attended
- Number photos to match the Photo ref column and keep them in one shared folder
- Set the print area to landscape, fit to one page wide, with the header row repeating on each page
- Save one master file; send exports or PDFs, never editable copies, to subs
Template variants for different jobs
Residential remodel punch list
On a kitchen, bath or whole-house remodel the homeowner usually walks with the GC. Keep it simple: Room, Item, Trade, Status, Homeowner OK. The extra "Homeowner OK" column, initialed by the owner, records that they accept the fix, which helps when the final payment depends on the list being cleared. Group the list by room: kitchen, primary bath, hall bath, bedrooms, exterior.
Commercial tenant improvement (TI) punch list
A TI job has more parties: the GC, the tenant, the landlord's representative and often the architect. Add a Raised by column (Architect, Tenant, Landlord, GC) and a Spec / drawing ref column so items tie back to the contract documents. Split the list by area (open office, conference rooms, break room, restrooms, corridors) and keep landlord base-building items separate from tenant-scope items, since different people pay for them.
Room-by-room punch list
For multifamily, hotels and dorms, the same rooms repeat. Make one sheet per unit or room, with the categories pre-filled down the left side: walls and paint, ceiling, floor, doors and hardware, windows, electrical, plumbing, HVAC, millwork, cleaning. The person walking ticks each category as OK or writes an item. Pre-filled categories stop people from skipping the ceiling or the back of the door.
| Variant | Columns to add or drop | Group by |
|---|---|---|
| Residential remodel | Add Homeowner OK; drop Responsible party if the GC handles all trades | Room |
| Commercial TI | Add Raised by, Spec/drawing ref, Scope (tenant or landlord) | Area or suite |
| Room-by-room | Pre-filled category rows per room; Status per category | Unit or room number |

How to run the punch walk with this template
- Walk it yourself first. The GC and superintendent do an internal walk before the architect or owner sees the job. Fix the obvious items before the formal walk so the official list stays short.
- Agree the route and the people. Set a time with the architect, owner's rep and key subs. Walk in a fixed order, such as top floor down, clockwise in each room, so nothing is skipped.
- Bring what you need. A printed or digital copy of the template, the floor plans, a phone or camera, painter's tape or dot stickers to mark items, a flashlight and a level.
- Write each item where you stand. Location, defect, trade. Take the photo and note its number in the same moment. Don't rely on memory back at the trailer.
- Mark the defect physically. A small piece of tape or a sticker with the item number lets the sub find it without the list.
- Settle disputes on the spot or park them. If someone says an item is new scope, note it as "disputed" and move on. Resolve it through a change order later, not on the walk.
- Issue the list the same day. Clean it up, assign every item to a sub with a due date, and send it out as a PDF while the walk is fresh.
For background on where the punch walk fits between substantial completion and final completion, see what is a punch list.
How to close out punch list items
The list is only useful if items move to Closed in a way everyone trusts. A simple workflow:
- Open: item written and assigned.
- In progress: the sub has started or scheduled the fix.
- Ready for review: the sub says it is done, ideally with an "after" photo.
- Closed: the GC (or the architect, for items they raised) checks it on site and initials and dates the Verified column.
If a fix fails review, set it back to Open with a note ("still rubs at head") rather than writing a new item, so the history stays on one line. Before asking for the final inspection, filter for anything not Closed, walk those items again and attach the updated list to your request. Keep the final version, with photos, in the closeout file alongside warranties and lien waivers: it is your record of what was fixed and when.
Common template mistakes
- Renumbering items. Deleting rows and re-sorting changes every reference. Never reuse a number; mark items Closed or Void instead.
- One-word descriptions. "Paint" or "door" means nothing three weeks later. Write the defect and the fix.
- Photos in a separate place with no link. If the Photo ref column is blank, the photo is effectively lost.
- Subs closing their own items. Let subs mark items Ready for review; only the GC or architect closes them.
- No due dates. Items without dates sit at the bottom of every sub's list.
From spreadsheet to phone
The spreadsheet works, but on site you end up writing notes, taking photos on a phone and typing it all up later. A punch list app puts the photo, the location and the item in one place as you walk. Snagline, our phone app for punch lists and site audits, numbers items for you, pins them on the floor plan and exports a PDF report or a CSV file for Excel. It is not released yet; join the waitlist below.
Questions
What should be included in a punch list template?
At minimum an item number, location, description, trade and status. Most GCs also add the responsible sub, priority, photo reference, date added, due date and who verified the fix.
How do you write a punch list item?
Write the location, the defect and what done looks like, then assign the trade: for example, Room 214, north wall: outlet cover plate missing, install plate, Electrical. Add a photo with the defect marked.
Is there a punch list template in Excel?
You can build one in a few minutes: paste the eleven column headers from this page into row 1, add drop-downs for Priority and Status, and freeze the header row. The same layout works in Google Sheets.
Who fills out the punch list?
The general contractor usually writes and maintains it, with items added by the architect and owner during the punch walk. Subs update the status of their own items, and the GC or architect verifies and closes them.
What is the difference between a punch list and a checklist?
A checklist lists what to inspect, such as walls, doors and fixtures, before anyone looks. A punch list lists what was actually found wrong and must be fixed.