What is a punch list? How it works at substantial completion and closeout
A punch list is the list of work that is still unfinished or not up to the contract when a construction project is almost done: a missing outlet cover, a scuffed door, a leaking trap. The contractor prepares it around substantial completion, the owner or architect walks the job and adds items, and the work is finished and checked before final payment and closeout.

What a punch list is, in plain terms
Every building job ends with a long tail of small things. The walls are up, the systems run and the owner could move in, but a cabinet door rubs, a light fixture has no lens and the paint has holidays behind the radiator. A punch list collects those items in one place so they get fixed, checked and signed off instead of being forgotten.
On a commercial job the punch list is a formal closeout document. On a residential remodel it may be one page the homeowner and the general contractor (GC) write together on the final walkthrough. Either way, each entry answers the same questions: where is it, what is wrong, who fixes it and when it is done.
Typical entries read like this:
- Unit 204, kitchen: dishwasher not secured to countertop, Plumbing/Appliance sub
- Corridor 2B: ceiling tile stained above sprinkler head, Acoustical ceiling sub
- Primary bath: grout missing at tub corner, Tile sub
- Lobby: door closer slams, adjust speed, Door hardware sub
A punch list is not a list of major unfinished work. If the roof is not on or the HVAC does not run, the project is not ready for a punch list yet. The list assumes the building is basically usable and covers what remains to make it fully match the plans and specifications.
Where does the term "punch list" come from?
Nobody knows for certain. The term shows up in US court records from the late 1930s, according to the etymologist Michael Quinion (World Wide Words). The popular explanation is that contractors punched a hole in the margin next to each item as it was completed, but no one has found documents that prove it, so treat it as a plausible story rather than a fact.
When does the punch list happen in a project?
The punch list belongs to the end of construction, between substantial completion and final completion. On a job that uses AIA contract documents (widely used standard forms in US construction), the sequence usually runs like this:
- The contractor believes the work is substantially complete. The building, or a portion the owner agrees to accept separately, can be occupied or used for its intended purpose.
- The contractor prepares the punch list. The GC walks the job, usually with the superintendent and key subs, and lists everything still to be completed or corrected.
- The architect inspects (the punch walk). The architect, often with engineering consultants and the owner's representative, walks the work against the contractor's list and adds anything missing.
- Certificate of Substantial Completion. When the work passes, the architect issues the certificate (AIA G704 is the standard form). It sets the date of substantial completion, who is responsible for security, maintenance, utilities and insurance from then on, and the time allowed to finish the items on the attached list. Under A201-2017, warranties generally start on the date of substantial completion unless the certificate says otherwise.
- Punch work. Subs return to fix their items. The GC tracks each one to done.
- Final inspection. The contractor notifies the architect that the work is ready. The architect checks the punch items and the rest of the work.
- Final completion, final payment and closeout. With the list cleared and closeout documents handed over (lien waivers, warranties, O&M manuals, as-builts, attic stock), the architect certifies final payment and the remaining retainage is released.
Contracts that do not use AIA forms (ConsensusDocs, owner-written contracts, simple residential agreements) follow much the same pattern with different names and deadlines. Read your own contract for the exact steps.
Who creates the punch list, and who reviews it?
Under the AIA A201-2017 General Conditions, Section 9.8.2, when the contractor considers the work substantially complete it must "prepare and submit to the Architect a comprehensive list of items to be completed or corrected prior to final payment." The same section adds that leaving an item off the list does not change the contractor's responsibility to complete all the work in line with the contract documents.
Section 9.8.3 then has the architect inspect to decide whether the work is substantially complete. If the inspection finds items, whether or not they were on the contractor's list, that stop the owner from using the work for its intended purpose, the contractor must fix them and ask for another inspection before the certificate is issued.
In practice the roles look like this:
| Party | Role on the punch list |
|---|---|
| General contractor | Writes the first list, assigns items to subs, tracks them and requests re-inspection |
| Subcontractors | Fix their items and report them complete to the GC |
| Architect | Inspects, adds items, certifies substantial completion and final payment |
| Engineers (MEP, structural) | Walk their systems and add items on larger jobs |
| Owner or owner's rep | Walks with the architect, adds items, accepts the work |
On a home remodel there is often no architect in the contract. The homeowner and the GC walk together, agree on the list in writing and use it to decide when the final payment is due.

What goes on a punch list?
Most items are finish and fit issues, plus systems that are installed but not quite right. Use these categories as a prompt on your walk:
- Paint: touch-ups, missed spots, overspray on hardware, outlets or glass
- Drywall: nail pops, visible seams, dings, poor patches around penetrations
- Flooring: chips, scratches, lifted transitions, gaps at baseboard, stained grout
- Doors and hardware: rubbing or sagging doors, missing stops, closers out of adjustment, locks not keyed
- Millwork and cabinets: misaligned doors and drawers, missing shelves, damaged countertops
- Electrical: missing cover plates, fixtures without lenses or lamps, outlets not working, panel schedule not labeled
- Plumbing: drips, slow drains, loose fixtures, missing escutcheons, no hot water at a sink
- HVAC: missing grilles, thermostats not set up, rooms too hot or cold, filters not replaced
- Ceilings: stained, cracked or missing tiles, gaps at walls
- Glazing: scratched or cracked glass, labels still on, failed seals
- Exterior: sealant gaps, damaged siding, downspouts not connected, landscaping damage
- Life safety and code: missing signage, fire extinguisher cabinets, exit lights not working
- Cleaning: construction dust, debris above ceilings, stickers and protection film left on
Some things should not be on the punch list. Large incomplete scopes belong on the schedule, not the list. Disputed or new scope belongs in a change order. Defects found after final completion are usually warranty claims, handled under the contract's correction period.
Punch list vs snag list: same idea, different country
A snag list is the British term for the same thing: the list of defects and unfinished items at the end of a job. The idea is identical; the paperwork around it differs.
| Punch list (US) | Snag list (UK) | |
|---|---|---|
| Usual trigger | Substantial completion | Practical completion or handover |
| Who certifies | Architect (AIA contracts) | Contract administrator or employer's agent |
| New homes | Builder walkthrough with the buyer | Buyer or a snagging surveyor inspects; builder warranty covers early defects |
| Money held back | Retainage | Retention |
| Verb | "Punching out" a job | "Snagging" a property |
If you work with UK clients, our guide to what snagging is explains the British side.
How the punch list ties to retainage and payment
Retainage is the part of each progress payment the owner holds back until the end of the job, so the contractor has a reason to finish. It is often in the range of 5% to 10%, but the rate, any cap and the release date depend on the contract and, in many states, on statute. Rules for public projects often differ from private work.
The punch list is where retainage meets reality. Under A201-2017 Section 9.8.5, once the owner and contractor accept the Certificate of Substantial Completion (and the surety consents, if there is one), the owner pays the retainage for that work, adjusted for work that is incomplete or not in line with the contract. In practice that adjustment is often an amount held back against the open punch items. Under Section 9.10.2, final payment and any remaining retainage are not due until the contractor provides the closeout paperwork, such as an affidavit that bills and payrolls are paid and evidence that required insurance stays in force.
Many contracts change these terms, so always check:
- The retainage rate and whether it drops partway through the job
- Whether retainage is released at substantial completion, final completion or in stages
- How much is held against open punch items
- The deadline to finish punch work (often stated on the substantial completion certificate)
- Your state's prompt payment and retainage rules, especially on public work
For subs, this is why punch items matter: an unfinished item on one trade can hold up money for everyone further down the chain.

Rolling and zero punch lists
Waiting until the end to find every defect makes for a long, expensive punch walk. Two habits reduce it.
Rolling punch list
The GC punches areas as each one is finished: a floor, a unit or a wing. Items get fixed while the trade is still on site, and the final walk mostly confirms earlier work. It works well on multifamily, hotels and phased tenant improvements.
Zero punch list
A goal rather than a document: deliver work so clean that the final walk finds little or nothing. It depends on quality checks at each stage, such as inspecting drywall before paint and ceilings before tile goes in, so problems never get covered up. Few jobs get to zero, but aiming for it changes how trades work.
Common punch list mistakes
- Vague entries. "Fix paint" helps nobody. Write the room, the surface and the defect: "Room 112, north wall: roller marks at eye height, repaint wall."
- No photos. A photo with an arrow ends most "which one?" arguments.
- No owner for each item. Every line needs a trade or sub, or it drifts.
- Treating the list as complete. Under AIA terms, an item missing from the list is still the contractor's responsibility.
- No verification step. A sub saying "done" is not the same as the GC or architect checking it. Keep "fixed" and "closed" separate.
- Several versions of the list. The architect's copy, the GC's spreadsheet and a sub's notes drift apart. Keep one list everyone works from.
- Starting too late. A single punch walk at the very end produces hundreds of items at once. Punch as you go.
Writing your first punch list
Start with our punch list template: it gives the columns most GCs use, a filled-in example and a step-by-step punch walk. If you'd rather capture items on your phone, with photos, plan pins and a PDF to send the architect, see how a punch list app works. Snagline, our phone app for punch lists and site audits, is in development; you can join the waitlist below.
Questions
What is a punch list in construction?
It is the list of work still to finish or correct when a project is substantially complete, such as touch-up paint, missing cover plates or doors that rub. The contractor fixes every item before final completion and final payment.
Who is responsible for creating the punch list?
Under the AIA A201 General Conditions the contractor prepares the list and submits it to the architect, who inspects and can add items. On residential jobs without an architect, the homeowner and contractor usually write it together on the final walkthrough.
What is the difference between substantial completion and final completion?
Substantial completion means the owner can occupy or use the work for its intended purpose, with only punch list items left. Final completion means the punch list is cleared, closeout documents are handed over and final payment can be certified.
How long does a contractor have to finish punch list items?
It depends on the contract. On AIA jobs the Certificate of Substantial Completion sets the time allowed; other contracts state a number of days. Check your own contract.
Is a punch list the same as a snag list?
Yes, in practice. Punch list is the US term and snag list the UK term for the list of defects and unfinished items at the end of a building job.
Can an owner withhold payment for punch list items?
Usually some money is held back until the items are done, through retainage or a holdback tied to the open items. How much and for how long depends on the contract and state law.