Snagging list template: columns, a worked example and how to use it

Updated · Snagline guides

A good snagging list template has ten columns: No., Location, Description, Trade, Priority, Photo ref, Reported, Due, Status and Signed off. Copy the layout below into Excel, Google Sheets or Word, write one snag per row, and send the list to your developer or contractor. A filled-in example with real snags follows the blank template.

Man reviewing architectural plans at desk in sunlight, displaying concentration and creativity

The template

Copy this header row into a spreadsheet (one column each) or a landscape table in a document. Add a header block above it with the property address, plot number, developer or contractor, the date of inspection and who carried it out.

No.LocationDescriptionTradePriorityPhoto refReportedDueStatusSigned off
1Open
2Open
3Open

What each column is for

ColumnWhat to writeExample
No.A unique number that never changes, even when the item is closed7
LocationFloor and room, then the exact spotFirst floor, bedroom 2, wall behind door
DescriptionOne fault, in one plain sentence, with a measurement if it helpsSocket cover missing, wires visible
TradeWho should fix itElectrician
PriorityCritical, High, Medium or LowHigh
Photo refPhoto file name or number, so the picture and the row matchP07a, P07b
ReportedDate you sent it to the builder02/03
DueDate agreed for the fix16/03
StatusOpen, In progress, Fixed, ClosedFixed
Signed offInitials and date of the person who checked the fixJM 18/03

Priority scale

Status meanings

Keeping Fixed and Closed separate is the most useful habit in snagging. Items marked done that were never checked are where most disputes start.

Filled-in example

Here is the template completed for a three-bedroom new-build house, three weeks after a pre-completion inspection. Dates are day/month.

No.LocationDescriptionTradePriorityPhoto refReportedDueStatusSigned off
1Kitchen, under sinkDrip from waste connection, cupboard base wetPlumberCriticalP01a, P01b02/0304/03ClosedJM 05/03
2Lounge, rear windowHandle stiff, window will not lock closedWindowsHighP0202/0309/03Fixed
3Bathroom, bathSilicone missing at tap end, about 20 cmPlumberHighP0302/0309/03ClosedJM 10/03
4Bedroom 2, wall behind doorSocket cover missing, wires visibleElectricianHighP0402/0304/03ClosedJM 05/03
5En-suiteExtractor fan does not run with the lightElectricianMediumP0502/0316/03In progress
6Kitchen, wall unit left of extractorDoor drops 4 mm at handle side, catches next doorJoinerMediumP0602/0316/03Open
7Bedroom 1, wardrobe wallUneven plaster patch, about 40 cm, visible in daylightPlastererMediumP07a, P07b02/0323/03Open
8Landing, skirtingPaint run 30 cm left of bathroom doorDecoratorLowP0802/0323/03Open
9Rear patio by back doorStanding water after rain, slabs fall towards houseGroundworksHighP0909/0323/03Open
10Front elevation, below lounge sillMortar missing from bed joint, about 15 cmBricklayerMediumP1009/0323/03Open

Note that item 2 is Fixed but not signed off: the window has been adjusted, but the buyer has not tried it yet. Items 9 and 10 were added a week later, with their own reported date, and keep the next numbers in sequence.

Confident female construction worker inspecting site with clipboard and helmet
A printed template on a clipboard still works well for a walk-round.

How to use the template

  1. Fill in the header: address, plot, builder, inspection date, your name.
  2. Walk the property in a fixed order: outside first, then each floor room by room. Our new build snagging checklist gives the order and what to check in each room.
  3. Write one snag per row. Two faults in one place are two rows, often for two different trades.
  4. Photograph every row. Name or number the photos to match the Photo ref column, so P07a is the wide shot and P07b the close-up of snag 7.
  5. Set priorities honestly. If everything is High, nothing is.
  6. Sort by trade before sending if the builder asks for it: one electrician can then clear all the electrical rows in one visit. Keep the numbers as they are.
  7. Update the status after each visit and send a fresh version, so there is only ever one current list.

For tips on wording each description, see how to write a snag list.

Making a printable version

A paper copy is handy on site, where typing on a laptop is awkward.

Sending the list to a developer or contractor

New-build homes

Contractors and subcontractors

Construction worker in safety gear checking smartphone on a Detroit site
Number photos to match the Photo ref column, or they get lost.

Spreadsheet tips

Common mistakes with snag list templates

Doing it on a phone instead

The template works on paper or in a spreadsheet. The weak point is always matching photos to rows. Snagline, a phone app we are building, does the template's job in one place: take the photo first, add location, trade, priority and due date, and the numbers, statuses and overdue flags are handled for you. It produces a PDF report with photos per item and a sign-off, and exports CSV for Excel. It is not released yet; join the waitlist below.

Questions

What columns should a snagging list template have?

No., Location, Description, Trade, Priority, Photo ref, Reported, Due, Status and Signed off. Add a header with the address, builder, inspection date and inspector.

Is there a free snag list template in Excel?

Copy the ten column headings on this page into Excel or Google Sheets and add drop-down lists for Trade, Priority and Status. That is all a snag list template needs.

How do I send a snagging list to my developer?

Use the after-sales channel in your home user guide, attach photos or a PDF with photos per item, ask for a reference number and keep the date you sent it.

Should I print my snagging list?

A printed copy is useful on site. Use landscape A4, leave room to write, repeat the headers on each page, then type the list up and send it in writing.

What is the difference between a snag list template and a punch list template?

They do the same job. Snag list is the UK term and punch list the US term; on US projects the punch list is usually tied to substantial completion and reviewed by the architect.