Site inspection report: how to carry out a construction site inspection and write it up
A site inspection report records what an inspector found on a walk round a construction site: hazards, poor workmanship and work that does not match the drawings, each with a location, priority, photo, owner and due date. Plan the route, walk it with a site inspection checklist, deal with anything dangerous on the spot, then write up numbered findings the same day and re-inspect.

What a site inspection report covers
On a construction site, "inspection" can mean several things, and the report should say which one it is:
- General health and safety inspection: a walk round looking at access, housekeeping, work at height, plant, fire and welfare.
- Quality or workmanship inspection: checking work against drawings, the specification and manufacturers' instructions, often before it is covered up.
- Progress inspection: what has been done since the last visit (closer to a site visit report).
- Statutory inspections: some equipment and work areas must be inspected by a competent person at set times, with set report contents. Scaffolds and excavations are the most common examples (see below).
Many site managers combine safety and quality in one weekly walk round. That is fine, as long as the report keeps the two kinds of finding clearly labelled, because they go to different people and have different urgency.
Who carries out site inspections
In Great Britain, the Construction (Design and Management) Regulations 2015 (CDM 2015) set out who is responsible for health and safety on a construction project. HSE's summary of the duties describes the principal contractor, appointed by the client on projects with more than one contractor, as responsible for planning, managing, monitoring and coordinating health and safety during the construction phase. That includes making sure suitable site inductions are given, taking reasonable steps to prevent unauthorised access, and providing welfare facilities. Contractors must plan, manage and monitor the work under their control. Clients keep duties of their own, including making sure the principal designer and principal contractor carry out theirs.
CDM 2015 does not prescribe a weekly site inspection form. Regular inspections are simply one of the most common ways contractors show they are monitoring the work. Clients' representatives, insurers, auditors and in-house safety advisers also carry them out. For what applies to your project, read HSE's guidance on CDM 2015 and the Managing health and safety in construction guidance (L153) on hse.gov.uk, and your own company's procedures.
Statutory inspections: scaffolds and excavations
Two inspections that site managers meet most often have their own legal requirements. These are summaries; check the source before relying on them.
- Scaffolds. HSE's scaffolding guidance says scaffolds must be inspected by a competent person after installation and before first use, then at intervals of no more than 7 days, and after any event likely to affect safety, such as high winds. The inspection report should record any defects or risks found and the action taken, even if it was put right straight away. The requirements come from the Work at Height Regulations 2005.
- Excavations. Regulation 22 of CDM 2015 says construction work in a supported or battered excavation must not go ahead unless it has been inspected by a competent person at the start of the shift, after any event likely to have affected its strength or stability, and after any material unintentionally falls or is dislodged. Regulation 24 sets out what the report must contain (who it was for, the location and area inspected, date and time, risks found and action taken, and the inspector's name and position), says it must be provided within 24 hours, and that it must be kept on site until the work is complete and for 3 months after.
A general site inspection does not replace these. It is reasonable, though, for your walk round to check that the scaffold tag or register and excavation inspection records are up to date.
Before you go: planning the inspection
- Read the last report. List its open items; check those first.
- Know what is happening today. Look at the programme, the construction phase plan and any permits (hot work, confined space, excavation) so you know which activities to look at.
- Plan a route that covers the whole site, including the parts people rarely visit: the back of the compound, the roof, the stair cores.
- Take the right kit: PPE for the site, a phone or tablet with charge, a tape measure, a torch, and the drawings if you are checking workmanship.
- Tell the site manager you are there, sign in and follow the site's induction and visitor rules.
Site inspection checklist
Use this as a starting point and adapt it to your site, the work in progress and your company's procedures. It is a prompt for what to look at, not a statement of legal requirements; for those, see HSE's construction guidance on hse.gov.uk.
Site access, security and traffic
- Perimeter fencing and gates complete and secure; signs at entrances
- Signing-in system in use; visitors inducted
- Pedestrian routes separated from vehicles and plant where possible
- Traffic routes, banksman arrangements and reversing areas as planned
- Safe access to the public highway; mud and debris controlled
Housekeeping
- Walkways, stairs and access routes clear
- Materials stored safely and stacked stably
- Waste removed regularly; skips not overfilled
- Trailing cables and hoses routed or covered
- Adequate lighting in work areas and access routes
PPE
- People wearing the PPE required by the site rules and risk assessments
- PPE in good condition; spares available for visitors
- Task-specific PPE in use (eye, hearing, respiratory protection) where assessed
Scaffolding and working at height
- Scaffold inspection records or tags up to date
- Guardrails, toe boards and brick guards in place; no missing boards
- Edge protection at slab edges, openings and stairwells
- Openings in floors covered, fixed and marked
- Ladders in good condition, used for suitable short-duration work and secured
- Mobile towers and MEWPs set up as the manufacturer intends; operators trained
Excavations
- Excavation inspection records up to date
- Sides supported or battered back as planned
- Barriers and edge protection to stop people, vehicles and materials falling in
- Spoil and materials kept back from the edge
- Safe means of getting in and out
- Underground services located and marked before digging
Plant and equipment
- Plant operated by trained, authorised people
- Daily checks recorded where required; defects reported
- Lifting equipment examined and lifting operations planned
- Hand tools and power tools in good condition; guards fitted
- Temporary electrics protected and inspected
Fire
- Fire points with extinguishers and alarms in place and accessible
- Escape routes clear and signed
- Hot work permits in use and fire watch carried out
- Flammable materials and gas cylinders stored correctly
- Waste and packaging not building up near work or escape routes
Welfare
- Toilets and washing facilities with hot and cold water, soap and drying
- Drinking water available
- Somewhere to rest and eat, and to store and dry clothing
- Welfare facilities clean and stocked
- First aid kit and trained first aiders identified
Health
- Dust controlled at source (water suppression, extraction) during cutting and drilling
- Noisy and vibrating work controlled as assessed
- Hazardous substances stored and used as the assessments say
- Manual handling reduced with lifting aids where planned
Quality and workmanship
- Work matches the current drawings and specification revision
- Materials as specified; approved samples available for comparison
- Manufacturers' installation instructions followed
- Work to be covered up inspected and recorded first
- Fire stopping and cavity barriers installed and recorded before they are hidden
- Completed work protected from damage by following trades
- Previous defects fixed and checked

During the inspection
- Deal with danger first. If something puts someone at immediate risk, stop it and tell the person in control of the site before you carry on. Record what you saw, who you told and when.
- Record as you go. One finding per item, with location, a photo and a short description, while you are standing in front of it.
- Talk to people. Ask operatives how a task is being done and whether anything gets in the way. Workers often know about a problem before anyone writes it down.
- Note good practice too. A short positive line in the report helps it read as fair, and tells the team what to keep doing.
Writing up the site inspection report
Use a fixed structure so every report is comparable with the last:
- Header: site, address, project reference, inspected by, date and time, weather, who was present.
- Scope: the areas and activities inspected, and any you could not get to.
- Summary: two or three sentences plus counts of findings by priority.
- Findings table: number, location, finding, category (safety, quality, welfare), priority, photo, action, owner, due date, status.
- Immediate actions taken on the day.
- Open items from the previous report and their current status.
- Sign-off: name, role, signature, date.
Example findings:
| No. | Location | Finding | Category | Priority | Action / owner / due |
|---|---|---|---|---|---|
| 1 | Level 2, east stair core | Floor opening cover lifted and not fixed; no marking | Safety | Critical | Refixed and marked during inspection; site manager to brief trades today |
| 2 | Compound | Gas cylinders stored next to waste skip | Fire | High | Move to cylinder cage; logistics manager; today |
| 3 | Level 1, flat 104 | Cavity barrier above window head not installed before boarding started | Quality | High | Stop boarding, install, photograph; drylining subcontractor; 2 days |
| 4 | Welfare cabin | No hot water at wash basins | Welfare | High | Repair heater; site manager; tomorrow |
| 5 | Ground floor corridor | Cables trailing across main walkway | Housekeeping | Medium | Route at high level; electrical subcontractor; today |
The general structure is the same as the inspection report template, which also has a filled example and priority definitions.

Follow-up: closing the loop
A site inspection report earns its keep on the next visit. Start the next inspection by walking to every open item. Mark an item Fixed when the owner says it is done and Closed only once you have seen it. If the same finding keeps coming back (trailing cables, blocked fire points), that is a pattern for the site manager to deal with at its cause, through briefings, layout or supervision, rather than another line in the report.
Common mistakes
- Ticking a checklist without findings. A list of ticks says nothing about what was wrong or who will fix it.
- Writing up days later. Details and photos get lost; record on site.
- No owner or due date. Every finding needs both.
- Mixing up urgency. A missing guardrail and a paint run should not sit side by side at the same priority.
- Inspecting only the usual route. Vary it, and cover the parts of the site people rarely see.
- Not recording what was done on the day. If you stopped work or made something safe, say so.
Doing site inspections on a phone
Paper and spreadsheets work. If you would rather record findings with photos as you walk, Snagline (iPhone and Android, not released yet) gives each finding a number, photos you can mark up, priority, location, assignee and due date, works offline, and shares a PDF report with issue counts and a signed sign-off. Join the waitlist below.
Questions
What is a site inspection report?
A record of what an inspector found on a walk round a construction site: hazards, poor workmanship and work that does not match the drawings, each with a location, priority, photo, owner and due date.
What should a site inspection checklist include?
Site access and security, housekeeping, PPE, scaffolding and working at height, excavations, plant and equipment, fire, welfare, health risks such as dust and noise, and quality and workmanship.
How often should a construction site be inspected?
It depends on the site, the work and your company's procedures; weekly general inspections are common. Some inspections have set intervals, for example HSE guidance says scaffolds must be inspected at least every 7 days.
Who is responsible for site inspections under CDM 2015?
On projects with more than one contractor, the principal contractor plans, manages, monitors and coordinates health and safety in the construction phase, and contractors monitor the work under their control. CDM 2015 does not prescribe a specific inspection form.
How do you write a site inspection report?
Use a fixed structure: header, scope, summary with counts by priority, a numbered findings table with owners and due dates, immediate actions taken, the status of previous items, and a sign-off. Write it the same day.
What is the difference between a site inspection and a site audit?
The terms overlap. An inspection is usually a walk round looking at conditions on the day; an audit usually also checks paperwork and whether the management system (plans, permits, inductions, records) is working.