Construction daily report template (with a filled sample report)

Updated · Snagline guides

A construction daily report records one working day on site. Include the date and report number, weather, crew counts by trade, hours, equipment, materials delivered, work completed by area, inspections, visitors, delays and their causes, safety incidents and near misses, RFIs and verbal instructions, photos and a signature. Download the free template above, then see the filled sample report below.

Female engineer in safety gear at a construction site with steel structure background

What a construction daily report is, and who reads it

A construction daily report (also called a daily log, daily field report or superintendent's daily) is a one- or two-page record of a single working day on site. The superintendent, foreman or site lead fills it in at the end of each shift, and the GC keeps the full set for the life of the project.

It is written for several readers at once:

That last reader is why daily reports matter. Most delay claims and many change order disputes come down to what happened on particular days: who was on site, what weather stopped work, which instruction was given. If the daily reports are complete and consistent, the facts are already written down.

What to include in a daily construction report

Use these fields. The free download above has them laid out as a fill-in form in Word, Excel and PDF.

FieldWhat to record
Project and report detailsProject name and number, report number (sequential), date, day of the week, who prepared it
WeatherConditions in the morning and afternoon, high and low temperature, precipitation, wind; note whether weather stopped or limited work
Crew counts by tradeEach company on site, its trade, number of workers and foreman's name
HoursStart and finish times, total hours per crew, any overtime or second shift
EquipmentMajor equipment on site, whether it worked or sat idle, and why
Materials deliveredSupplier, what arrived, quantity, delivery ticket number, and anything damaged, short or rejected
Work completed by areaWhat each trade did and where (level, grid line, unit, room), with quantities where they help
Inspections and testsInspector or agency, what was inspected, pass, fail or partial, and any follow-up
VisitorsName, company, purpose, time in and out (owner, architect, engineers, inspectors, suppliers)
Delays and causesWhat was delayed, for how long, why, and who was notified
SafetyIncidents, injuries, near misses, toolbox talk topic, hazards found and fixed
RFIs, instructions and changesRFIs raised or answered, verbal instructions received, possible change orders, with who said what
PhotosNumber of photos taken and what they show; link or attach them
SignatureName, title, signature and date of the person responsible for the report

Some companies add a schedule line (planned vs actual activities for the day), a "tomorrow" section, and a notes box for anything that does not fit. Keep the core fields the same on every report so they are easy to compare across weeks.

Daily report checklist for the end of the shift

Run through this before you sign. If a box does not apply, write "none" rather than leaving it blank: a blank field reads as "not recorded," while "none" says you checked.

Daily construction report sample (filled example)

Here is a filled sample for an imaginary three-story medical office building. Names and figures are illustrative.

Report details

FieldEntry
ProjectRiverside Medical Office Building, Job 24-117
Report no.DR-142
DateTuesday, March 11
Prepared byJ. Alvarez, Superintendent
WeatherAM overcast, 41°F; PM light rain from 1:30, 48°F; wind 10–15 mph. Rain stopped exterior sealant work at 1:45 pm.

Manpower

CompanyTradeWorkersHours
GC (own forces)General labor, carpentry47:00–3:30
Summit DrywallFraming and drywall97:00–3:30
Delta MechanicalHVAC57:00–3:30
Brightline ElectricElectrical66:30–3:00
Coastal GlazingExterior sealant37:00–1:45 (rain)

Work completed

Equipment and deliveries

Inspections, visitors, delays

Safety, RFIs, photos

Signed: J. Alvarez, Superintendent, March 11.

Construction worker in safety gear checking smartphone on a Detroit site
Take and label photos during the day so they are ready when you write the report.

Tips for daily reports that hold up later

Daily report vs site diary vs site visit report

These three documents overlap, and the names vary between companies and countries. The usual split:

Construction daily reportSite diarySite visit report
Who writes itSuperintendent or foremanSite manager or superintendentVisiting architect, engineer, PM or client rep
How oftenEvery working dayEvery day, often running notesAfter each visit
FormatStructured form with fixed fieldsFreer, chronological notesObservations plus an actions list
Main purposeRecord labor, work, weather, delays and safety for the project recordPersonal or site record of events, conversations and instructionsProgress seen on the day and actions with owners and dates
Main readersPM, owner, claimsSite team, later claimsClient, design team, contractor

On US jobs the daily report is usually the formal record. On UK jobs the site diary plays much the same role. If you visit a site rather than run it, use the site visit report template instead.

Common daily report mistakes

Doing daily reports on a phone

Paper forms and spreadsheets work, and the template above is enough for many jobs. The weak point is photos: they sit on someone's phone with no link to the report. Snagline, our phone app for site audits, snag lists and punch lists, is aimed at defects and issues rather than full daily logs, but its photo-first issues and PDF reports cover the "items found today" part of a daily report. It is coming to iPhone first; join the waitlist below.

Questions

What should be included in a construction daily report?

Date and report number, weather, crew counts and hours by trade, equipment, deliveries, work completed by area, inspections, visitors, delays with causes, safety incidents and near misses, RFIs and instructions, photos and a signature.

Who writes the daily report on a construction site?

Usually the general contractor's superintendent or foreman. Subcontractors often keep their own daily reports as well and send them to the GC.

How long should a construction daily report be?

One or two pages is typical. It should be long enough to record every crew, delay and event, and short enough to finish at the end of the shift.

Is a daily report the same as a site diary?

They overlap. A daily report is usually a structured form with fixed fields; a site diary is often freer notes. In the UK the site diary often serves as the main daily record.

How long should daily reports be kept?

Keep them at least for the life of the project and any warranty or claims period after it. Check your contract, company policy and local rules for the exact retention period.