Construction daily report template (with a filled sample report)
A construction daily report records one working day on site. Include the date and report number, weather, crew counts by trade, hours, equipment, materials delivered, work completed by area, inspections, visitors, delays and their causes, safety incidents and near misses, RFIs and verbal instructions, photos and a signature. Download the free template above, then see the filled sample report below.

What a construction daily report is, and who reads it
A construction daily report (also called a daily log, daily field report or superintendent's daily) is a one- or two-page record of a single working day on site. The superintendent, foreman or site lead fills it in at the end of each shift, and the GC keeps the full set for the life of the project.
It is written for several readers at once:
- The project manager uses it to track progress against the schedule, spot problems early and back up pay applications.
- The owner or owner's rep reads it to see what happened on a day they were not on site.
- Subcontractors check it when crew counts, deliveries or delays affect their own billing.
- Safety and insurance staff look for incidents, near misses and toolbox talks.
- Lawyers and claims consultants, months or years later, if there is a dispute over a delay, a change order or a defect. A report written on the day carries far more weight than a memory reconstructed afterwards.
That last reader is why daily reports matter. Most delay claims and many change order disputes come down to what happened on particular days: who was on site, what weather stopped work, which instruction was given. If the daily reports are complete and consistent, the facts are already written down.
What to include in a daily construction report
Use these fields. The free download above has them laid out as a fill-in form in Word, Excel and PDF.
| Field | What to record |
|---|---|
| Project and report details | Project name and number, report number (sequential), date, day of the week, who prepared it |
| Weather | Conditions in the morning and afternoon, high and low temperature, precipitation, wind; note whether weather stopped or limited work |
| Crew counts by trade | Each company on site, its trade, number of workers and foreman's name |
| Hours | Start and finish times, total hours per crew, any overtime or second shift |
| Equipment | Major equipment on site, whether it worked or sat idle, and why |
| Materials delivered | Supplier, what arrived, quantity, delivery ticket number, and anything damaged, short or rejected |
| Work completed by area | What each trade did and where (level, grid line, unit, room), with quantities where they help |
| Inspections and tests | Inspector or agency, what was inspected, pass, fail or partial, and any follow-up |
| Visitors | Name, company, purpose, time in and out (owner, architect, engineers, inspectors, suppliers) |
| Delays and causes | What was delayed, for how long, why, and who was notified |
| Safety | Incidents, injuries, near misses, toolbox talk topic, hazards found and fixed |
| RFIs, instructions and changes | RFIs raised or answered, verbal instructions received, possible change orders, with who said what |
| Photos | Number of photos taken and what they show; link or attach them |
| Signature | Name, title, signature and date of the person responsible for the report |
Some companies add a schedule line (planned vs actual activities for the day), a "tomorrow" section, and a notes box for anything that does not fit. Keep the core fields the same on every report so they are easy to compare across weeks.
Daily report checklist for the end of the shift
Run through this before you sign. If a box does not apply, write "none" rather than leaving it blank: a blank field reads as "not recorded," while "none" says you checked.
- Date, day and report number filled in
- Weather recorded for morning and afternoon
- Every company on site listed with its head count
- Start and finish times for each crew
- Equipment on site and any idle time explained
- Deliveries listed with ticket numbers and any damage noted
- Work completed described by area, not just by trade
- Inspections and results recorded
- Visitors logged with times
- Delays recorded with cause, duration and who was told
- Safety incidents and near misses recorded, or "none"
- RFIs, verbal instructions and possible changes written down
- Photos taken, labeled and attached
- Report signed and dated
Daily construction report sample (filled example)
Here is a filled sample for an imaginary three-story medical office building. Names and figures are illustrative.
Report details
| Field | Entry |
|---|---|
| Project | Riverside Medical Office Building, Job 24-117 |
| Report no. | DR-142 |
| Date | Tuesday, March 11 |
| Prepared by | J. Alvarez, Superintendent |
| Weather | AM overcast, 41°F; PM light rain from 1:30, 48°F; wind 10–15 mph. Rain stopped exterior sealant work at 1:45 pm. |
Manpower
| Company | Trade | Workers | Hours |
|---|---|---|---|
| GC (own forces) | General labor, carpentry | 4 | 7:00–3:30 |
| Summit Drywall | Framing and drywall | 9 | 7:00–3:30 |
| Delta Mechanical | HVAC | 5 | 7:00–3:30 |
| Brightline Electric | Electrical | 6 | 6:30–3:00 |
| Coastal Glazing | Exterior sealant | 3 | 7:00–1:45 (rain) |
Work completed
- Level 3, grid A–D: Summit hung drywall on corridor walls; Level 3 east exam rooms framed and ready for MEP inspection.
- Level 2: Delta installed duct risers in shafts 1 and 2; branch duct 60% complete in east wing.
- Level 1: Brightline pulled feeders from main switchgear to panels L1A and L1B.
- Exterior, south elevation: Coastal completed sealant at storefront bays 1–4; bays 5–8 stopped for rain.
Equipment and deliveries
- Scissor lifts (3) in use on Level 3. Telehandler idle all day, no picks scheduled.
- ABC Supply, 220 sheets 5/8" Type X drywall, ticket 55821. 6 sheets with broken corners set aside, supplier notified.
Inspections, visitors, delays
- City building inspector, Level 2 above-ceiling rough-in: partial pass. Fire caulking missing at two penetrations in corridor 2B; re-inspection requested for Thursday.
- Visitors: M. Chen (owner's rep), 10:00–11:15, walked Level 3. R. Patel (architect), 1:00–2:00, reviewed storefront.
- Delay: exterior sealant stopped 1:45 pm due to rain, about 2 hours lost for Coastal (3 workers). Reported to PM by text at 1:50.
Safety, RFIs, photos
- Toolbox talk: ladder safety (24 attendees). Near miss: unsecured drywall sheet fell from cart on Level 3, no injury; carts now strapped. No recordable incidents.
- RFI 088 submitted: conflict between duct and beam at grid C-4, Level 2. Architect verbally directed the outlet relocation on the exam room 3-12 wall; confirmation requested in writing.
- Photos: 18 taken (fire caulking deficiencies, broken drywall delivery, storefront sealant, duct conflict at C-4).
Signed: J. Alvarez, Superintendent, March 11.

Tips for daily reports that hold up later
- Write it the same day. A report filled in on Friday for the whole week loses detail and credibility.
- Stick to facts. "Electrician not on site; called foreman at 8:15, no answer" is useful. "Electrician unreliable again" is opinion and invites an argument.
- Record causes and times for every delay. Duration, cause, which trades were affected and who you told. This is the part of the report most often read in a claim.
- Write down verbal instructions. If the architect or owner tells you to change something on site, record who said it and what, then ask for written confirmation.
- Count heads from the site, not the schedule. Walk the job or check the sign-in sheet; don't copy yesterday's numbers.
- Tie photos to the report. A photo with a date and a short caption is worth more than a folder of unlabeled images.
- Be consistent. Same template, same fields, same level of detail every day, even on quiet days.
- Keep reports unchanged once signed. If you need to correct something, add a note to the next day's report rather than editing the old one.
Daily report vs site diary vs site visit report
These three documents overlap, and the names vary between companies and countries. The usual split:
| Construction daily report | Site diary | Site visit report | |
|---|---|---|---|
| Who writes it | Superintendent or foreman | Site manager or superintendent | Visiting architect, engineer, PM or client rep |
| How often | Every working day | Every day, often running notes | After each visit |
| Format | Structured form with fixed fields | Freer, chronological notes | Observations plus an actions list |
| Main purpose | Record labor, work, weather, delays and safety for the project record | Personal or site record of events, conversations and instructions | Progress seen on the day and actions with owners and dates |
| Main readers | PM, owner, claims | Site team, later claims | Client, design team, contractor |
On US jobs the daily report is usually the formal record. On UK jobs the site diary plays much the same role. If you visit a site rather than run it, use the site visit report template instead.
Common daily report mistakes
- "Same as yesterday." Copy-pasted reports are easy to spot and hard to defend.
- Missing subs. Leaving a small crew off the manpower list makes the report useless for checking their billing.
- Weather without effect. "Rain" is not enough. Say what it stopped and for how long.
- Delays without cause. "Waiting on materials" without which materials, from whom and since when.
- Safety left blank. Write "no incidents, no near misses" so the record is clear.
- Unsigned reports. An unsigned report is harder to rely on later. Sign and date every one.
Doing daily reports on a phone
Paper forms and spreadsheets work, and the template above is enough for many jobs. The weak point is photos: they sit on someone's phone with no link to the report. Snagline, our phone app for site audits, snag lists and punch lists, is aimed at defects and issues rather than full daily logs, but its photo-first issues and PDF reports cover the "items found today" part of a daily report. It is coming to iPhone first; join the waitlist below.
Questions
What should be included in a construction daily report?
Date and report number, weather, crew counts and hours by trade, equipment, deliveries, work completed by area, inspections, visitors, delays with causes, safety incidents and near misses, RFIs and instructions, photos and a signature.
Who writes the daily report on a construction site?
Usually the general contractor's superintendent or foreman. Subcontractors often keep their own daily reports as well and send them to the GC.
How long should a construction daily report be?
One or two pages is typical. It should be long enough to record every crew, delay and event, and short enough to finish at the end of the shift.
Is a daily report the same as a site diary?
They overlap. A daily report is usually a structured form with fixed fields; a site diary is often freer notes. In the UK the site diary often serves as the main daily record.
How long should daily reports be kept?
Keep them at least for the life of the project and any warranty or claims period after it. Check your contract, company policy and local rules for the exact retention period.