A punch list is the list of work still unfinished or not up to the contract when a construction project is nearly done: a missing outlet cover, a door that rubs, a dripping trap. The contractor prepares it at substantial completion, the architect and owner walk the job and add items, and every item is fixed and checked before final payment, retainage release and closeout.

Punch list app: add, track and close out punch list items on iPhone · 0:44 · steps, captions and transcript on the video page
Confident female construction worker inspecting site with clipboard and helmet

Punch list meaning: a simple definition

A punch list (also written punchlist or punch-list) is a document that lists the work still to be finished or corrected before a construction contract is complete. Merriam-Webster defines it as "a list of usually minor tasks to be completed at the end of a project," and dates the first known use to 1955. In construction the word has a narrower, contractual meaning: the items that stand between substantial completion and final completion.

Each punch list item, sometimes called a punch item, answers four questions: where it is, what is wrong, who fixes it and when it is done. "Punching out" a job means working through the list until every item is closed.

The definition has three parts worth remembering:

In construction, what is a punch list for?

Every building job ends with a long tail of small things. The walls are up, the systems run and the owner could move in, but a cabinet door rubs, a light fixture has no lens and the paint has holidays behind the radiator. A punch list collects those items in one place so they get fixed, checked and signed off instead of being forgotten.

On a commercial job the punch list is a formal closeout document. On a residential remodel it may be one page the homeowner and the general contractor (GC) write together on the final walkthrough. Either way, each entry answers the same questions: where is it, what is wrong, who fixes it and when it is done.

Typical entries read like this:

A punch list is not a list of major unfinished work. If the roof is not on or the HVAC does not run, the project is not ready for a punch list yet. The list assumes the building is basically usable and covers what remains to make it fully match the plans and specifications.

Where does the term "punch list" come from?

Nobody knows for certain. The term shows up in US court records from the late 1930s, according to the etymologist Michael Quinion (World Wide Words), and dictionaries date common use to the 1950s. The popular explanation is that contractors punched a hole in the margin next to each item as it was completed, but no one has found documents that prove it, so treat it as a plausible story rather than a fact.

The punch list lifecycle, step by step

The punch list belongs to the end of construction, between substantial completion and final completion. On a job that uses AIA contract documents (widely used standard forms in US construction), the sequence usually runs like this:

  1. The contractor believes the work is substantially complete. The building, or a portion the owner agrees to accept separately, can be occupied or used for its intended purpose.
  2. The contractor prepares the punch list. The GC walks the job, usually with the superintendent and key subs, and lists everything still to be completed or corrected.
  3. The architect inspects (the punch walk). The architect, often with engineering consultants and the owner's representative, walks the work against the contractor's list and adds anything missing.
  4. Certificate of Substantial Completion. When the work passes, the architect issues the certificate (AIA G704 is the standard form). It sets the date of substantial completion, who is responsible for security, maintenance, utilities and insurance from then on, and the time allowed to finish the items on the attached list. Under A201-2017, warranties generally start on the date of substantial completion unless the certificate says otherwise.
  5. Punch work. Subs return to fix their items. The GC tracks each one to done.
  6. Final inspection. The contractor notifies the architect that the work is ready. The architect checks the punch items and the rest of the work.
  7. Final completion, final payment and closeout. With the list cleared and closeout documents handed over (lien waivers, warranties, O&M manuals, as-builts, attic stock), the architect certifies final payment and the remaining retainage is released.

Contracts that do not use AIA forms (ConsensusDocs, owner-written contracts, simple residential agreements) follow much the same pattern with different names and deadlines. Read your own contract for the exact steps.

Punch list lifecycle: substantial completion, punch walk, punch list issued, items fixed, back-check, final completion, final payment and retainage release, closeout
From substantial completion to closeout: the punch list sits between the punch walk and final completion.

Who creates the punch list, and who reviews it?

Under the AIA A201-2017 General Conditions, Section 9.8.2, when the contractor considers the work substantially complete it must "prepare and submit to the Architect a comprehensive list of items to be completed or corrected prior to final payment." The same section adds that leaving an item off the list does not change the contractor's responsibility to complete all the work in line with the contract documents.

Section 9.8.3 then has the architect inspect to decide whether the work is substantially complete. If the inspection finds items, whether or not they were on the contractor's list, that stop the owner from using the work for its intended purpose, the contractor must fix them and ask for another inspection before the certificate is issued.

In practice the roles look like this:

PartyRole on the punch list
General contractorWrites the first list, assigns items to subs, tracks them and requests re-inspection
SubcontractorsFix their items and report them complete to the GC
ArchitectInspects, adds items, certifies substantial completion and final payment
Engineers (MEP, structural)Walk their systems and add items on larger jobs
Owner or owner's repWalks with the architect, adds items, accepts the work

On a home remodel there is often no architect in the contract. The homeowner and the GC walk together, agree on the list in writing and use it to decide when the final payment is due.

Group of engineers and architects wearing safety gear at a construction site, discussing plans
The punch walk: GC, architect and owner's rep go through the work against the list.

What goes on a punch list?

Most items are finish and fit issues, plus systems that are installed but not quite right. Use these categories as a prompt on your walk:

Some things should not be on the punch list. Large incomplete scopes belong on the schedule, not the list. Disputed or new scope belongs in a change order. Defects found after final completion are usually warranty claims, handled under the contract's correction period.

To print these categories with columns for location, trade, due date and status, download the free punch list in Word, Excel or PDF above, or see the full punch list template page.

Punch list examples

Good entries are specific enough that a sub who was not on the walk can find the item, fix it and know what "done" looks like. Here is how a short list reads on three kinds of job.

Commercial tenant improvement

#LocationItemTradeStatus
1Suite 300, conference roomTwo ceiling tiles cracked at light fixture, replaceAcoustical ceilingsOpen
2Suite 300, break roomSink trap drips when faucet runs, tighten or replacePlumbingIn progress
3Corridor outside 302Door closer slams, adjust closing speedDoor hardwareFixed
4Open office, east wallOutlet cover plate missing at column 4ElectricalClosed

Residential remodel

New home walkthrough

Notice what every example has: a room or grid location, the defect, the fix where it is not obvious and a responsible trade. A status column shows where each item stands; keep "fixed" (the sub says it is done) separate from "closed" (someone checked it).

Punch list vs snag list: same idea, different country

A snag list is the British term for the same thing: the list of defects and unfinished items at the end of a job. The idea is identical; the paperwork around it differs.

Punch list (US)Snag list (UK)
Usual triggerSubstantial completionPractical completion or handover
Who certifiesArchitect (AIA contracts)Contract administrator or employer's agent
New homesBuilder walkthrough with the buyerBuyer or a snagging surveyor inspects; builder warranty covers early defects
Money held backRetainageRetention
Verb"Punching out" a job"Snagging" a property

If you work with UK clients, our guide to what snagging is explains the British side.

How the punch list ties to retainage and payment

Retainage is the part of each progress payment the owner holds back until the end of the job, so the contractor has a reason to finish. It is often in the range of 5% to 10%, but the rate, any cap and the release date depend on the contract and, in many states, on statute. Rules for public projects often differ from private work.

The punch list is where retainage meets reality. Under A201-2017 Section 9.8.5, once the owner and contractor accept the Certificate of Substantial Completion (and the surety consents, if there is one), the owner pays the retainage for that work, adjusted for work that is incomplete or not in line with the contract. In practice that adjustment is often an amount held back against the open punch items. Under Section 9.10.2, final payment and any remaining retainage are not due until the contractor provides the closeout paperwork, such as an affidavit that bills and payrolls are paid and evidence that required insurance stays in force.

Many contracts change these terms, so always check:

For subs, this is why punch items matter: an unfinished item on one trade can hold up money for everyone further down the chain.

After the punch list: the correction period

Clearing the punch list does not end the contractor's responsibility. Under A201-2017 Section 12.2.2, if work turns out not to match the contract documents within one year after the date of substantial completion (or a longer period set by a warranty or the contract), the contractor must correct it promptly after the owner gives written notice. If the owner finds such a problem and does not tell the contractor, the owner can lose the right to make the contractor correct it.

The one-year correction period is often mistaken for a one-year warranty. AIA's own commentary says it relates only to the duty to come back and fix work; claims about defects found later are governed by the contract and by the state's statutes of limitation and repose. Many contracts amend these clauses, so check yours.

Practically, this means two lists: the punch list, which closes out the job, and a warranty or callback list for problems reported after occupancy. Keep them separate so a late warranty item does not reopen the closeout paperwork.

Rolling and zero punch lists

Waiting until the end to find every defect makes for a long, expensive punch walk. Two habits reduce it.

Rolling punch list

The GC punches areas as each one is finished: a floor, a unit or a wing. Items get fixed while the trade is still on site, and the final walk mostly confirms earlier work. It works well on multifamily, hotels and phased tenant improvements.

Zero punch list

A goal rather than a document: deliver work so clean that the final walk finds little or nothing. It depends on quality checks at each stage, such as inspecting drywall before paint and ceilings before tile goes in, so problems never get covered up. Few jobs get to zero, but aiming for it changes how trades work.

Common punch list mistakes

Writing your first punch list

Start with the free download above or our punch list template: it gives the columns most GCs use, a filled-in example and a step-by-step punch walk. If you'd rather capture items on your phone, with photos, plan pins and a PDF to send the architect, see how a punch list app works. Snagline, our phone app for punch lists and site audits, is in development for iPhone; you can join the waitlist below.

Questions

What does punch list mean?

A punch list is a list of usually minor work still to be done or corrected at the end of a project. In construction it is the list of items between substantial completion and final completion that must be cleared before final payment.

Who is responsible for creating the punch list?

Under the AIA A201 General Conditions the contractor prepares the list and submits it to the architect, who inspects and can add items. On residential jobs without an architect, the homeowner and contractor usually write it together on the final walkthrough.

What is the difference between substantial completion and final completion?

Substantial completion means the owner can occupy or use the work for its intended purpose, with only punch list items left. Final completion means the punch list is cleared, closeout documents are handed over and final payment can be certified.

How long does a contractor have to finish punch list items?

It depends on the contract. On AIA jobs the Certificate of Substantial Completion sets the time allowed; other contracts state a number of days. Check your own contract.

Is it punch list or punchlist?

Both spellings are used and mean the same thing. Dictionaries list it as two words, punch list; punchlist and punch-list are common variants in the industry.

Can an owner withhold payment for punch list items?

Usually some money is held back until the items are done, through retainage or a holdback tied to the open items. How much and for how long depends on the contract and state law.