A health and safety audit is a structured check of whether your health and safety arrangements are in place, followed and working. Unlike a quick inspection, it looks at paperwork and the management system as well as conditions on site. Plan the scope, check documents, walk the site, talk to people, score what you find, then give every finding an owner and a due date. Use the checklist below.

How to create a site inspection report with photos (PDF) on your phone · 0:42 · steps, captions and transcript on the video page
Row of orange safety vests and blue helmets hanging in industrial setting

What a health and safety audit is

An audit asks three questions: do we have the right arrangements (policy, risk assessments, method statements, training, inspections, emergency plans), are people following them, and do they actually control the risks? It compares what you find against a standard: the law, HSE guidance, your client's requirements, your own procedures, or a management system standard such as ISO 45001.

HSE's guidance on managing health and safety (HSG65, Managing for health and safety) is built around Plan, Do, Check, Act. Audits sit in the Check step, alongside inspections, monitoring and investigating accidents and near misses. HSE notes that paperwork on its own is not a good measure of performance, so a good audit always looks at the work too.

This page uses the law and guidance for Great Britain. Northern Ireland has its own equivalent legislation, enforced by HSENI. Nothing here is legal advice; check HSE guidance and get competent advice for your own circumstances.

Audit vs inspection vs risk assessment

A practical way to tell them apart:

Risk assessmentInspectionAudit
QuestionWhat could cause harm, and what controls do we need?Are conditions safe today?Is the whole system in place and working?
WhenBefore work starts; reviewed when things changeOften: daily, weekly, or at set statutory intervalsLess often: quarterly, every six months, yearly, or per project stage
Looks atHazards, who could be harmed, controlsThe site, equipment and work in progressDocuments, records, training, supervision and conditions on site
Done byEmployer (with competent help)Supervisors, site managers, competent personsSomeone independent of the work: in-house adviser, senior manager or external auditor
OutputRecorded significant findings and controlsList of defects and actionsScored report with findings, root causes and an action plan

In short: the risk assessment decides the controls, inspections check the controls are there on the day, and the audit checks that both of those processes are happening and working. For the weekly walk round, see the site inspection report guide.

No law in Great Britain says "carry out an annual health and safety audit". But several duties point the same way:

An audit is one of the clearest ways to show that monitoring and review are happening. HSE says larger organisations should have formal procedures for auditing and reporting health and safety performance, and periodic audits of risk controls. For small, low-risk businesses, HSE says you are not required to have a formal management system; a simple Plan, Do, Check, Act approach can be enough.

Who carries out safety audits

Whoever does it needs to be competent: they should know the work, the risks and the relevant law and guidance well enough to judge what they see.

How to plan a health and safety audit

  1. Set the scope. One site, one activity (for example lifting operations), one contractor, or the whole business.
  2. Choose the criteria. What are you auditing against: your policy and procedures, the construction phase plan, HSE guidance, a client's rules, ISO 45001?
  3. Read before you go. The last audit and its open actions, recent inspection reports, accident and near-miss records, and the programme so you know which high-risk work is happening.
  4. Agree the date with the site or workplace manager, unless you are deliberately doing an unannounced audit. Make sure the people you need to interview will be there.
  5. Prepare the checklist. Start from the one below, cut what does not apply and add your own procedures. Download the Word or Excel version above to edit it.
  6. Decide the scoring before you start, so every audit is comparable.

Running the audit on site or in the workplace

  1. Opening meeting: the scope, timetable and how findings will be reported.
  2. Documents and records: policy, risk assessments, method statements, the construction phase plan, inductions, training and competence cards, permits, inspection registers (scaffold, excavation, lifting equipment), accident records. Sample them: pick three operatives and check their induction and training; pick two high-risk tasks and check the method statement matches what is happening.
  3. Walk round: compare what the paperwork says with what you see. Cover the whole site, not only the usual route.
  4. Talk to people: ask operatives and supervisors how a task is done, what they would do in an emergency, and how they report a problem.
  5. Deal with danger straight away. If you see something that puts someone at immediate risk, stop it and tell the person in control before carrying on. Record it as a finding with the action taken.
  6. Closing meeting: walk the manager through the main findings before you leave, so there are no surprises in the report and urgent actions start the same day.
Female engineer in safety gear at a construction site with steel structure background
Compare what the paperwork says with what is happening on site.

Scoring, findings and actions

A simple, consistent scale works better than a clever one. A common pattern:

Percentage scores are popular because they show a trend, but treat them with care: a site can score 95% and still have one critical finding. Always report the critical and major findings by name, not just the score, and mark questions that do not apply as N/A rather than counting them as passes.

Each finding should be written so someone can act on it without phoning you:

No.AreaFindingRatingActionOwnerDue
1Working at heightMobile tower in plot 7 in use with one guardrail missing on the platformCriticalUse stopped; tower re-erected by trained person and checked before reuseSite managerToday
2Management and documentsTwo of three operatives sampled had no record of site inductionMajorInduct both; review sign-in process so nobody starts without inductionSite managerWithin 2 days
3COSHHMortar admixture data sheet not on site; COSHH assessment refers to old productMinorObtain current safety data sheet; update assessment and brief usersContracts managerWithin 7 days
4Housekeeping and accessGround floor walkways clear and marked; waste segregatedCompliantNoneNoneNone

Where the same problem appears in several places, look for the cause: missing training, no supervision, the wrong equipment ordered, a procedure nobody can follow.

Writing the audit report and following up

Keep the report short and in the same order every time: site and scope, auditor, date, people interviewed, a summary with counts by rating, the findings table, good practice seen, the status of actions from the last audit, and a sign-off. Send it within a few days, while the findings are fresh.

Then close the loop:

How to use this health and safety audit checklist

The checklist below covers a typical construction site, and most sections also apply to workshops, yards and other workplaces. It is a prompt for what to look at, not a statement of what the law requires on your site. Remove what does not apply and add your own procedures. The free Word, Excel and PDF versions above contain the same items with tick boxes.

For the detail behind each area, use HSE's guidance on hse.gov.uk, including Managing health and safety in construction (L153) and Fire safety in construction (HSG168).

Management and documents

Site set-up and welfare

Working at height

Scaffolding

Excavations

Plant and equipment

Electrical safety

Fire

Hazardous substances (COSHH)

Manual handling

PPE

Housekeeping and access

Common mistakes

Recording audit findings on a phone

Paper and the downloadable checklist work well. If you would rather record findings with photos as you walk, Snagline is our phone app for site audits and snag lists (iPhone first, Android later; not released yet). Each finding gets a number, marked-up photos, a priority, location, assignee and due date; it works offline; and it produces a PDF report with issue counts and a signed sign-off. Join the waitlist below.

Questions

What is a health and safety audit?

A structured check of whether an organisation's health and safety arrangements are in place, followed and effective. It looks at documents, records, training and supervision as well as conditions on site, and ends with a scored report and an action plan.

What is the difference between a safety audit and a safety inspection?

An inspection checks conditions on the day, such as guardrails, housekeeping and PPE. An audit is less frequent and wider: it checks that risk assessments, inspections, training and other arrangements exist and are working.

Is a health and safety audit a legal requirement?

There is no specific legal requirement in Great Britain to hold an annual audit, but the Management of Health and Safety at Work Regulations 1999 require arrangements for monitoring and review. HSE says larger organisations should have formal audit procedures. This is not legal advice.

How often should you carry out a health and safety audit?

It depends on the size of the business and the risks. Many firms audit each site every few months or at key project stages and audit the whole business yearly; higher-risk work or poor results justify more frequent audits.

Who can carry out a health and safety audit?

Any competent person who is independent of the work being audited: an in-house health and safety adviser, a manager from another site, or an external consultant. Clients and principal contractors also audit contractors on construction projects.

What should a health and safety audit checklist include?

Management and documents, site set-up and welfare, working at height, scaffolding, excavations, plant and equipment, electrical safety, fire, hazardous substances, manual handling, PPE, and housekeeping and access, adapted to your own work.