Site diary: what to record on a construction site every day
A site diary is the daily written record of what happened on a construction site: weather, who was on site, plant, deliveries, visitors, instructions received, work done, delays and safety events. It is written on the day, by the site manager or foreman, and kept for the life of the project. When questions about time, money or quality come up later, it is often the best evidence anyone has.

What a site diary is (and is not)
A construction site diary is a factual, dated log kept every working day. It is usually the site manager's responsibility on a main contract, but subcontractors, clerks of works and small builders keep their own too. It differs from the other paperwork on site:
- Daily report: often a form sent to the client or head office each day. A site diary can feed it, but the diary is the fuller record that stays with the job. Our construction daily report template covers the report format.
- Site visit report: written by a visitor (architect, engineer, client's representative) after an inspection. See the site visit report template.
- Snag list: a list of faults to fix, usually near the end. See snag list.
The diary is not a place for opinions about other parties or for arguments. Write what happened, when, who was involved and what it affected.
Why a site diary matters
Most of the time nobody reads the diary. It earns its keep when something is disputed months later and memories have faded.
- Delay and extension of time. If the job runs late, both sides need to show what actually happened day by day: rain stopping work, a late delivery, an instruction that changed the sequence, a site closed for a utility strike. Construction lawyers and guidance such as the Society of Construction Law's Delay and Disruption Protocol stress the value of good contemporaneous records, meaning records made at the time.
- Weather. A claim that weather held up work is much harder to support if nobody wrote down the conditions and what work stopped. Note temperature, rain, wind and the effect on the work, not just "wet".
- Variations and instructions. Verbal instructions are common on site. Recording who said what, and when, helps when the formal instruction or the payment for the extra work follows later.
- Quality and defects. Notes and photos of work before it is covered up (drainage, insulation, fire stopping) help answer questions after handover.
- Health and safety. Toolbox talks, near misses, accidents and inspections belong in the diary, alongside the formal reports your safety system requires.
What a diary is worth in any dispute depends on the contract, the facts and how the records were kept. This is general information, not legal advice; check your contract's notice and record-keeping clauses, which often have strict time limits of their own.
What to record in a site diary every day
Use the same headings every day so gaps stand out. This is the checklist to work through before you leave site:
- Date, project name and reference, who is writing the entry
- Weather: morning and afternoon conditions, temperature, rain, wind; time lost to weather
- Site hours: when the site opened and closed
- Labour: number of people on site by company and trade
- Plant and equipment: what was on site, what was working, what was idle or broken down
- Deliveries: what arrived, from whom, when; anything late, short or damaged
- Visitors: name, company, purpose of the visit, time on site
- Instructions received: who gave them, how (verbal, email, drawing), what they changed
- Information requested or still awaited from the design team
- Work done today: by area and trade, against the programme
- Delays and disruption: what stopped or slowed work, for how long, which trades were affected
- Health and safety: inductions, toolbox talks, inspections, near misses, accidents
- Inspections and tests: building control, warranty inspectors, pressure tests, concrete pours
- Photos taken: what and where, so they can be found later
- Plan for tomorrow and anything that needs chasing
Example site diary entry
A real-world style entry for a small housing site. Copy the layout into your own diary or spreadsheet:
| Heading | Entry |
|---|---|
| Date / project | Tuesday 10 March, Plots 12–18, Mill Lane (ref ML-04). Written by site manager. |
| Weather | AM heavy rain, 6°C, strong wind. PM dry, 9°C. Bricklaying stopped 08:00–11:30 due to rain. |
| Site hours | 07:30–17:00 |
| Labour | Groundworks 4, bricklayers 6 (from 11:30), carpenters 3, electrician 2, site team 2. Total 17. |
| Plant | 1 x 9 t excavator (working), 1 x telehandler (working), 1 x dumper (hydraulic leak, off hire from 14:00). |
| Deliveries | Roof trusses for Plots 14–15 arrived 09:15, complete. Blocks due 10:00 did not arrive; supplier now says Thursday. |
| Visitors | Building control officer, 13:00–13:45, foundations Plot 18: passed. Client's representative, 15:00, walk-round. |
| Instructions | Client's representative asked verbally for an extra external socket on Plot 12 rear wall. Asked for written instruction; emailed 15:40. |
| Work done | Plot 18 foundations poured after inspection. Plots 14–15 first lift brickwork. Plot 12 first fix electrics 60% complete. |
| Delays | 3.5 hours bricklaying lost to rain (Plots 14–15). Plot 16 blockwork cannot start until blocks arrive. |
| Health and safety | Toolbox talk on working near the excavator (11 attended). Near miss: unsecured pallet on scaffold lift Plot 15, removed and reported. |
| Photos | Plot 18 foundations before pour (6); late block delivery note; scaffold near miss (2). |
| Tomorrow | Chase blocks. Scaffold inspection Plot 15. Continue brickwork if dry. |
The construction daily report download above has the same headings as a Word, Excel or PDF form if you prefer a ready-made template.
How to keep a site diary that holds up
- Write it on the day. An entry written a week later is weaker evidence and usually less accurate.
- Every working day, including quiet ones. "No work: site closed for rain" is a useful entry. A blank page is not.
- Facts, times and numbers. "Rain 08:00–11:30, bricklaying stopped" beats "bad weather today".
- Do not rewrite old entries. If something was wrong, add a dated correction underneath.
- Link photos. Dated photos with a short note of where they were taken make the diary much stronger.
- Keep it safe and keep it long. Store the diary for as long as claims could arise under your contract; ask your company's commercial or legal team how long that is.

Paper site diary, spreadsheet or app?
| Paper diary | Spreadsheet or Word template | Phone app | |
|---|---|---|---|
| Cost | Low | Low | Free to subscription |
| Photos | Separate, hard to link | Pasted in or referenced | Attached to the entry, dated |
| Searching later | Slow | Reasonable | Fast |
| Sharing | Scan or photocopy | Email the file | PDF or link from the phone |
| Risks | Lost, damaged, illegible | Written up later at a desk | Depends on the app and backups |
A bound paper diary with numbered pages is still common and easy to trust. Templates and apps make photos, searching and sharing easier. Whatever you use, the habit matters more than the format.
Using Snagline alongside your site diary
Snagline is a phone app we are building for site audits and snag lists, iPhone first. It is not a site diary, but it can hold the issues your diary refers to: numbered items with marked-up photos, optional timestamps and GPS location under photos, status and due dates, and PDF reports. It is not released yet; the waitlist is below.
Questions
What should be included in a site diary?
Date, weather, site hours, labour by trade, plant, deliveries, visitors, instructions received, work done, delays, health and safety events, inspections and tests, photos taken and the plan for the next day.
Who should keep the site diary?
On most projects the site manager or foreman keeps it for the main contractor. Subcontractors, clerks of works and small builders often keep their own as well.
Is a site diary a legal requirement?
There is no general rule that every site must keep a diary, but contracts often require records and notices, and a diary is one of the most useful records in a dispute. Check your contract.
What is the difference between a site diary and a daily report?
A daily report is usually a form sent to the client or head office each day. The site diary is the fuller record kept on site, which can feed the daily report.
Can I keep a site diary on my phone?
Yes. A phone makes it easier to attach dated photos and share entries. Write the entry on the day, do not edit old entries without noting the change, and make sure the records are backed up.