Site diary: what to record on a construction site every day

Updated · Snagline guides

A site diary is the daily written record of what happened on a construction site: weather, who was on site, plant, deliveries, visitors, instructions received, work done, delays and safety events. It is written on the day, by the site manager or foreman, and kept for the life of the project. When questions about time, money or quality come up later, it is often the best evidence anyone has.

Confident female construction worker inspecting site with clipboard and helmet

What a site diary is (and is not)

A construction site diary is a factual, dated log kept every working day. It is usually the site manager's responsibility on a main contract, but subcontractors, clerks of works and small builders keep their own too. It differs from the other paperwork on site:

The diary is not a place for opinions about other parties or for arguments. Write what happened, when, who was involved and what it affected.

Why a site diary matters

Most of the time nobody reads the diary. It earns its keep when something is disputed months later and memories have faded.

What a diary is worth in any dispute depends on the contract, the facts and how the records were kept. This is general information, not legal advice; check your contract's notice and record-keeping clauses, which often have strict time limits of their own.

What to record in a site diary every day

Use the same headings every day so gaps stand out. This is the checklist to work through before you leave site:

Example site diary entry

A real-world style entry for a small housing site. Copy the layout into your own diary or spreadsheet:

HeadingEntry
Date / projectTuesday 10 March, Plots 12–18, Mill Lane (ref ML-04). Written by site manager.
WeatherAM heavy rain, 6°C, strong wind. PM dry, 9°C. Bricklaying stopped 08:00–11:30 due to rain.
Site hours07:30–17:00
LabourGroundworks 4, bricklayers 6 (from 11:30), carpenters 3, electrician 2, site team 2. Total 17.
Plant1 x 9 t excavator (working), 1 x telehandler (working), 1 x dumper (hydraulic leak, off hire from 14:00).
DeliveriesRoof trusses for Plots 14–15 arrived 09:15, complete. Blocks due 10:00 did not arrive; supplier now says Thursday.
VisitorsBuilding control officer, 13:00–13:45, foundations Plot 18: passed. Client's representative, 15:00, walk-round.
InstructionsClient's representative asked verbally for an extra external socket on Plot 12 rear wall. Asked for written instruction; emailed 15:40.
Work donePlot 18 foundations poured after inspection. Plots 14–15 first lift brickwork. Plot 12 first fix electrics 60% complete.
Delays3.5 hours bricklaying lost to rain (Plots 14–15). Plot 16 blockwork cannot start until blocks arrive.
Health and safetyToolbox talk on working near the excavator (11 attended). Near miss: unsecured pallet on scaffold lift Plot 15, removed and reported.
PhotosPlot 18 foundations before pour (6); late block delivery note; scaffold near miss (2).
TomorrowChase blocks. Scaffold inspection Plot 15. Continue brickwork if dry.

The construction daily report download above has the same headings as a Word, Excel or PDF form if you prefer a ready-made template.

How to keep a site diary that holds up

  1. Write it on the day. An entry written a week later is weaker evidence and usually less accurate.
  2. Every working day, including quiet ones. "No work: site closed for rain" is a useful entry. A blank page is not.
  3. Facts, times and numbers. "Rain 08:00–11:30, bricklaying stopped" beats "bad weather today".
  4. Do not rewrite old entries. If something was wrong, add a dated correction underneath.
  5. Link photos. Dated photos with a short note of where they were taken make the diary much stronger.
  6. Keep it safe and keep it long. Store the diary for as long as claims could arise under your contract; ask your company's commercial or legal team how long that is.
Construction worker in safety gear checking smartphone on a Detroit site
Dated photos linked to the day's entry make a site diary far more useful later.

Paper site diary, spreadsheet or app?

Paper diarySpreadsheet or Word templatePhone app
CostLowLowFree to subscription
PhotosSeparate, hard to linkPasted in or referencedAttached to the entry, dated
Searching laterSlowReasonableFast
SharingScan or photocopyEmail the filePDF or link from the phone
RisksLost, damaged, illegibleWritten up later at a deskDepends on the app and backups

A bound paper diary with numbered pages is still common and easy to trust. Templates and apps make photos, searching and sharing easier. Whatever you use, the habit matters more than the format.

Using Snagline alongside your site diary

Snagline is a phone app we are building for site audits and snag lists, iPhone first. It is not a site diary, but it can hold the issues your diary refers to: numbered items with marked-up photos, optional timestamps and GPS location under photos, status and due dates, and PDF reports. It is not released yet; the waitlist is below.

Questions

What should be included in a site diary?

Date, weather, site hours, labour by trade, plant, deliveries, visitors, instructions received, work done, delays, health and safety events, inspections and tests, photos taken and the plan for the next day.

Who should keep the site diary?

On most projects the site manager or foreman keeps it for the main contractor. Subcontractors, clerks of works and small builders often keep their own as well.

Is a site diary a legal requirement?

There is no general rule that every site must keep a diary, but contracts often require records and notices, and a diary is one of the most useful records in a dispute. Check your contract.

What is the difference between a site diary and a daily report?

A daily report is usually a form sent to the client or head office each day. The site diary is the fuller record kept on site, which can feed the daily report.

Can I keep a site diary on my phone?

Yes. A phone makes it easier to attach dated photos and share entries. Write the entry on the day, do not edit old entries without noting the change, and make sure the records are backed up.