Defects liability period: what it is, how long it lasts and how retention is released

Updated · Snagline guides

A defects liability period (DLP) is a set time after practical completion, often 6 or 12 months, during which the contractor must come back and put right defects the client notifies. In JCT contracts it is now called the rectification period; NEC uses a defects date. The rest of the retention is usually released when it ends and the defects are made good.

Man reviewing architectural plans at desk in sunlight, displaying concentration and creativity

What the defects liability period means

When a building reaches practical completion, the client takes it over even though a few small defects may remain and others will show up in use. The defects liability period is the contract's mechanism for dealing with them: for a fixed period, the client (or their contract administrator) notifies defects, and the contractor returns to site and fixes them at its own cost.

It works in both parties' favour. The client gets defects fixed by the people who built the job, without a dispute. The contractor gets the chance to fix its own work, usually far cheaper than paying someone else to do it, and it gets its retention back at the end.

What it's called in different contracts

ContractTerm usedEnds with
JCT (recent editions, including 2016 and 2024)Rectification periodCertificate of making good (defects)
Older JCT and many bespoke contractsDefects liability periodCertificate of making good defects
NECDefects date, with a defect correction period for each notified defectDefects certificate
Other formsMaintenance period, defects notification periodVaries

The names differ but the idea is the same. Always read the contract particulars for your own job: the length, how defects must be notified and what the end certificate is called are set there.

How long is a defects liability period?

Commonly 6 or 12 months from practical completion, with 12 months usual on larger projects so the building goes through a full year of seasons and the heating and cooling are tested. Some contracts set longer periods for particular elements such as mechanical and electrical services or landscaping. Smaller works contracts often use shorter periods.

Standard forms fill in a default if the contract particulars are left blank, and the default differs between forms and editions. Don't rely on a default: write the period you want into the contract particulars.

Retention and the defects liability period

Retention is a percentage of each payment held back by the client as security for completing the work and fixing defects. It is typically released in two parts:

  1. At practical completion, part of the retention (often half) is released.
  2. At the end of the defects period, once the notified defects have been made good and the certificate issued, the balance is released.

The percentage, the split and any retention bond alternative are set by the contract. Disputes about final retention are common, usually because defects weren't recorded clearly or weren't signed off. A defects list with numbers, locations, photos and dates (notified, fixed, accepted) is the best protection on both sides.

Does liability end when the period ends?

No. The end of the period ends the contractor's right and obligation to return to site under that mechanism. It does not end the contractor's liability for defective work. A client can still bring a claim for defects found later, within the limitation period: in England and Wales generally six years from the breach for a simple contract and twelve years for a contract signed as a deed. Take legal advice on any specific claim.

For new homes sold to buyers there is a separate system: the developer's warranty (such as NHBC Buildmark, where the builder deals with defects in the first two years) and the New Homes Quality Code. See new build snagging for that side.

Managing defects during the period

Good practice for clients, contract administrators and contractors alike:

A defect is easiest to fix and least likely to be argued about when it is recorded the day it is found. Our snag list guide shows how to write entries a trade can act on, and defect tracking covers running the list over months.

End of defects period inspection

Most contracts expect a final schedule of defects at or soon after the end of the period. Walk the building with the contractor before the deadline, room by room, checking the items already fixed and adding anything new:

Snagline is built for this kind of list: each defect gets a number, marked-up photos, a status and a due date, and you can send a PDF schedule from site.

Questions

What is the defects liability period in construction?

A fixed period after practical completion, often 6 or 12 months, in which the contractor must return and fix defects the client notifies. JCT now calls it the rectification period.

How long is a defects liability period?

Commonly 6 or 12 months from practical completion, but it is whatever the contract says. Check the contract particulars.

When is retention released?

Typically part at practical completion and the balance at the end of the defects period, once notified defects are made good. The contract sets the amounts and timing.

Is the contractor liable after the defects liability period ends?

Usually yes. The period ends the contractor's right to return and fix defects under that clause, not its liability; claims can still be made within the limitation period.

What is the difference between snagging and the defects liability period?

Snagging is finding and listing defects, usually around completion. The defects liability period is the contractual time after completion in which the contractor must fix defects notified to it.